Create Replacement Order - Rent Out
Explanation
This activity is used when the customer wants to make 
an exchange of the rental assets sent out. This could happen if the asset has 
broken down or is due for scheduled maintenance. There can 
be other or several reasons as well. Then you need to send the 
customer a replacement.
This activity can also be used to create a replacement customer 
order to send the replacement parts to the customer. You need to handle the 
replacement customer order to deliver the replacement parts either from 
inventory or by supplying from internal or external supplier. 
If the original parts have been supplied from a site belonging to the same company 
or a different company compared to the demand site, you might want to request 
the replacement parts to be sent to the external customer from the original 
supply site. At this instance you need to manually create a replacement order 
against your original purchase order in the demand site and manually peg it to 
the external replacement customer order and proceed through the flow. But in 
case if you set the supply code of the external replacement customer order to Int Purch Trans
or Purch 
Order Trans, it will create a new rental contract with a new purchase order at 
demand site and when you send this purchase order to the supply site, it will 
not be identified as a replacement order request for the supply site.  
You also need to handle the customer receipt manually to get the exchanged parts 
back from the customer.
Managing the rental and the financial control of the 
replacement order line will be handled by the original rental number which 
corresponds to the original customer order line. 
Prerequisites
The original customer order must be at least partially 
delivered to the customer. 
System Effects
	- A replacement customer order rental line is 
	created. The header is created in Planned status.
- The rental line has 
	the demand code set to Replacement Customer Order. The 
	original rental number will be displayed in the customer order line level.
Window
Manage Rentals
Rental Workbench
Related Window Descriptions
Manage Rentals
Rental 
Workbench
Customer Order
 
Procedure
  - Open the  Manage Rental window and either 
	populate or query for the rental number or rental type as customer order. 
- Right-click and then click Create Replacement Order. The 
	
	Create Replacement Order dialog box is displayed. In the Quantity 
	to Replace field, specify a quantity in sales unit of measure. Confirm 
	by clicking
    OK.  A message displays the order number of the replacement 
	order and a question is asked whether you want to view the newly created 
	replacement order. Confirm by clicking OK.
- A new customer order in the Planned
	status is now available in the 
	
	Customer Order window. Treat this order as a normal customer rental 
	order.
 The wanted delivery date will be set as the 
	default value for planned rental start date of the replacement order line 
	and the planned rental end date will be copied 
	to the replacement order line. If the planned rental end date is less than 
	the planned rental start date, then the planned rental end date will be set 
	as equal to the planned rental start date.
Note:
	-  If the original external customer order 
was supplied from a different site and if you want to request the replacement 
parts from the supply site then you need to manually create a replacement 
purchase order for the original pegged purchase order and manually peg it to the 
external replacement customer order.
- In the inter-site flow, if you create a 
	replacement order for an internal customer order, it will create a 
	replacement order for the original purchase order in the demand site and it 
	will be sent to the supply site automatically in case any manual intervention 
	is not needed to proceed through the purchase order flow.