Approve/Accept Parts
Explanation
Use this activity to approve/accept 
parts that have been inspected and found to be as desired. The entire number of 
inspected parts will be available to be accepted and approved to be moved into 
stock, if handling inventory parts.
Prerequisites
  - The parts must have been reported as arrived in 
	Register
    Arrivals.
- The receipt line must have an inspection demand, either an
    inspection code or a quantity manually specified in the receipt function.
- The receipt line should be in status To be Inspected.
- IFS/Quality
    Management must have been installed to be able to use control plans, enter detailed
    analysis results, and to use SPC (Statistical Process Control).
System Effects
The inspection result is reported and the number of inspections
is increased (+1) every time an inspection is performed. The combination of the quantity
inspected and the number of inspections helps you when evaluating inspection/re-inspection
for a receipt line. A receipt line with inventory registered purchase parts receives the
status To be Received when the entry of inspection result is completed. This order is
ready to proceed in the work flow.
Non-inventory registered purchase parts and no-number parts
acquires the status Received. For receipt lines with these parts the receipt is completed.
If you are using IFS/Quality Management in the receipt
process, and if you have scrapped or returned any parts before an analysis is created, the
quantity to inspect indicated on the 
Receipt window
will be re-calculated based on the quantity available at the time you create a new
analysis. Any existing analyses will not be affected.
Window
Receipt
Inspection Management
Related Window Descriptions
Register Inspection 
Results, 
Receipt, 
Receipt/General, 
Receipt/Details,  
Inspection Management
Procedure
To approve the entire quantity. 
  - Populate or query for the order number in question. If you have
    several receipts for an order you also have to select the correct receipt number. In the 
  
	Receipt window and related tabs, do this by using the list box in the
    Order No field.
- Choose Register Inspection Results... in the Operations menu. The 
	Register
    Result dialog box opens up and the quantity to approve is displayed in the
    Approve fields, both in purchase unit and inventory unit.
- Confirm by clicking OK.
 Note: If the purchase order is generated from a shop order with an 
	outside operation which is the last operation, and the Receive into 
	Inventory on Last Operation check box is set to TRUE on the used work 
	center, a receive shop order dialog box will open. Entering the correct 
	location, the quantity and clicking OK will receive this shop order.
To approve a subset of the quantity, i.e., partially reporting the
inspection results. 
  - Populate or query for the order number in question. If you have
    several receipts for an order you also have to select the correct receipt number. In the 
  
	Receipt window and related tabs, do this by using the list box in the
    Order No field.
- Choose Register Inspection Results... in the Operations menu. The 
	Register
    Result dialog box opens up and the quantity to approve is suggested in the
    Approve fields, both in purchase unit and inventory unit. Decrease this value.
- Confirm by clicking OK.
 Note: If the purchase order is generated from a shop order with an 
	outside operation which is the last operation, and the Receive into 
	Inventory on Last Operation check box is set to TRUE on the used work 
	center, a receive shop order dialog box will open. Entering the correct 
	location, the quantity and clicking OK will receive this shop order.
(To scrap or return parts, see the corresponding activities.)
To view quality
management details:
  - In the Register Inspection Results
    dialog box, the Analysis exists check box will be selected if an analysis
    exists, and also if it has been confirmed.
- To view the confirmed analysis, click Analysis. Review the results and use it as a basis for the registration of
    the inspection results (approve, scrap, return).