View Capability Indices
Graph
Explanation
This activity is used to view capability indices for a specific Control Plan
line and to view them graphically.
Prerequisites
The corresponding Control Plan must exist, and at least two
Analyses must be complete for this specific Control Plan line. The Capability
Indices check box for the Control Plan line must also be selected.
System Effects
As a result of this activity, capability indices
are calculated for a specific Control Plan line in a Control Plan. They are also
displayed
graphically.
Window
Capability 
Indices Graph 
Capability Indices Graphs
Related Window Descriptions
Capability Indices Graph 
Capability Indices Graphs
Procedure
  - Select the Control Plan line.
- Right-click and then click Capability Indices Graphs.
- Sprcify a time period by selecting dates in the From 
	and To fields.
- Specify what frequency to use when creating the graph.
- Specify what specification limits to use when calculating the graph.
- Specify what capability indices values to be displayed by the graph.
- Click Create Graph to create the capability indices 
	graph.
- If you want to view the measurement data used for the calculations for a
    specific time period, select the line in the table, right-click and then 
	click Sample Data. The measurement data used for the calculations
    is displayed in the Result column.
- If you want to print the graph, right-click in the 
	header part of the 
	Capability Indices Graph window and then 
	click Print Capability Graph. A message will appear asking you 
	to confirm. Click Yes. The Report Print 
	dialog box will be 
	opened. Select the options as required and click OK.
- If you want to print sample data, right-click in 
	the header part of the window and then click Print Sample Data. A 
	message will appear asking you to confirm. Click Yes. The 
	Report Print 
	dialog box will be opened. Select the options as required and click OK.
Note: It is also possible to print the graph 
using the Order Reports window. In the Reports list, click 
the Capability Indices and enter the graph number.