Create Control Chart
Explanation
Use this activity to create a control chart for a specific control plan line.
When creating  Xbar and R chart, Xbar and S chart, np chart, and c chart, 
the defined sample size and resulting sample size will be used. 
	- p chart- Gives information about the proportion of nonconforming units.
- np chart- Gives information about the number of nonconforming units 
- c chart- Gives information about the number of nonconformities
- u chart- Gives information about the number of nonconformities per unit.
- Xbar and R chart - Gives information about the average and the range of 
	the result set of each analysis selected in the graph.
- Xbar and S chart - Gives information about the average and the standard 
	deviation of the result set of each analysis selected in the graph.
An analysis will not be included in creating a chart if any of the following 
conditions exist.: 
	- The status of the data point is incomplete. 
- The analysis header is canceled.
- The defined fixed sample size of the data point and the resulting sample 
	size of the analysis results do not match. (This does not apply for the p chart 
	and u chart.)
 
Prerequisites
	- To create a control chart for a specific control plan line, the corresponding 
	control plan must exist, and at least two analyses must be complete for this 
	specific control plan line. 
- The SPC check box for the control plan line must also be selected.
System Effects
As a result of this activity, a control chart for a specific control plan line 
is created depending on the sample size. 
Window
Control Plan - Manufacturing
Control Plan - Purchasing
Control Plan - Inventory
Xbar and R chart,
Xbar and S chart,
p chart,
c chart,
u chart, 
np chart
Related Window Descriptions
Control Plan - Manufacturing
Control Plan - Purchasing 
Control Plan - Inventory 
Xbar and R chart,
Xbar and S chart 
p chart,
u chart,
c chart,
np chart
Not included sample data- 
Attribute
Not included sample data- Variable
Procedure
	- Select the control plan line.
- Right-click and then click Create SPC Chart.
- Specify a time period by selecting the dates in the From and To 
	fields under the Analysis Date group box.
- Click OK to continue.
- Click OK to view the created control chart immediately, or No 
	to view it later.
- If you want to view the analysis numbers that were excluded when the control 
	charts were created, right-click and then click Not Included Sample Data.