Reorganize Project Structure
Explanation
Perform this activity to reorganize the project structure by moving 
subprojects and activities. This can be done by updating the Parent Sub Project 
ID field in the  
Sub Projects window and updating the 
Sub Project ID field in
the 
Activities
window. Alternatively, the drag and drop method can be used in 
the graphical structure navigator in the 
Project 
Navigator window.
Prerequisites
  - A project with project 
  structure must exist. 
System Effects
  - The project structure is 
  reorganized. 
Window
Project 
Navigator
Activities
Sub Projects
Related Window Descriptions
Project Navigator
Activities
Sub Projects
Procedure
	- To move an activity in Activities 
	- Enter the ID for the new subproject, or select from List of Values (F8).
- Save the changes.
	- To move a sub project in 
	Sub Projects 
	- Enter the new subproject ID in Parent Sub Project ID field or 
	select from List of values (F8).
- Save the changes.
	- To move an activity in 
	
	Project Navigator
  - Click the activity  
to be moved, drag it to the subproject, and drop the activity on the new parent.
	- To move a sub project in 
	Project 
	Navigator
  - Click the 
subproject to be moved, drag it to the subproject or the project, and drop 
it on the new parent.