Explanation
The menu option Delete Subproject Structure deletes a selected
subproject, including its structure and connected activities. A subproject without
structure can also be deleted through the Delete button (F7).
If any activity in the subproject is not allowed to be deleted due to, for 
example, progress reported on a task, then the subproject deletion is prevented 
through an error message. 
Also see related information found in Delete Activity. 
Prerequisites
  - If the menu option Delete Subproject Structure 
  is selected, any activities in the subproject must not have any baseline dates 
  set.
- If the Delete button is selected, the subproject 
  must not have a structure (activities).
- Any employee allocation registered to 
    the subproject 
    must be removed first.  
System Effects
  - If the menu option Delete Subproject Structure 
  is selected, the 
    subproject and its structure are deleted. All references to the subproject, including its
    structure and connected activities, are deleted.
- If the Delete button is selected, the 
  subproject is deleted.
- When deleting a subproject with the last remaining 
    activity that is used as basis for the
Date From and Date To values for an employee allocation registered 
    on the project or (another) subproject level, then the deletion is prevented 
    since the activity cannot be deleted.
Window
Subprojects
Project Navigator
Related Window Descriptions
Subprojects
Project Navigator
Procedure
Delete a sub project and its structure: 
  - Select the subproject to be deleted.
- Select the menu option Delete Subproject Structure.
- Answer Yes to the question.
Delete an empty sub project: 
  - Select the empty subproject.
- Press the Delete button.
- Answer Yes to the question.