Create Resource Forecast Versions
Explanation
This activity is used to create a new resource forecast version 
for a project. 
Prerequisites
	- A project should exist.
- A forecast type should be setup in Resources/Basic 
	Data/Resource Forecast Type.
System Effects
	- A resource forecast version is created.
Window
Project Resource Forecast 
Project Resource Forecasts
Related Window Descriptions
Project Resource Forecast
Project Resource Forecasts
Procedure
Use the following procedure to create a new resource forecast version using the 
 
Create Resource Forecast Assistant:
	- Open the Project Resource 
	Forecast 
	window.
- Right click on the window and select Create Resource Forecast. The first step 
	of the Create Project Resource Forecast Assistant opens up. 
- Select the Project ID for 
	which the resource forecast should be made and use the List button to select 
	project from a list.
- Select the Forecast Type field and use the List button to select a pre-defined 
	resource forecast types.
 
 Note: If the resource forecast version being created is of the same 
	resource forecast type 
	as an existing version, the forecast type of the existing resource forecast 
	version will be inherited into this field.
 
- Enter a description of the version you plan to create in the Version Description 
	field. 
- Enter a valid Cut-Off-Date. This value will 
	be referenced later on when creating snapshots on a particular project 
	forecast version. 
- Select the Copy From Forecast, if it's required to copy an 
	existing forecast to a new one. If the Copy check 
	box is not selected, an empty forecast will be created.
- Select the Create Snapshot check box, if it is required 
	to create a 
	snapshot of the forecast version. 
- In the Snapshot Description field it's possible to make a 
	description for the snapshot that will be taken.
- Click Next or Finish depending on your 
	selection for Copy check box.
If the Copy From Forecast option was selected
and Next> button was clicked the Copy From 
Resource Forecast step will be displayed:
	- You can modify the resource forecast version from which you want 
	to copy by using List button on the Forecast Version field.
	
         
	Note: If the resource forecast version being created is of the same 
resource forecast type as an existing version, the record of the existing 
resource forecast version will be inherited into the From Forecast Version 
field..
	- You can clear the Update with Activity Dates check box, to allow 
	the new resource forecast to use the start and end dates of the source 
	resource forecast line instead of the activity dates.
- Clear the Copy Hours Spread check box if it is required that the 
	hours spread on the source resource forecast should not be copied to the new 
	resource forecast. If selected, decide whether it should 
	be the Complete spread or 
	 
	From Cut Off Date.
- Clear the Set ETC check box if it is 
	required that the ETC field of the forecast lines are not to be 
	calculated based on previous forecast. If this check box is selected 
	then select one of the two options, based on your requirement:
 
		- Set ETC Based on Previous EAC: The EAC of the previous version is 
	copied as the EAC of the new forecast version. The ETC will then be 
	calculated to be the difference between the EAC and the hours until the 
	snapshot date and time. 
- Set ETC Based on Previous ETC: The ETC of the previous version is 
	copied as the ETC of the new forecast version. The EAC will then be 
	calculated to be the sum of the EAC and the hours until the snapshot date and 
	time.
If the Copy From Project Resource Planning option is selected, then 
click Next button, to display the Copy From Project Resource Planning 
step.
	- You can select to use either planned or baseline hours as the ETC hours 
	for the resource forecast version. Baseline hours can only be selected if a 
	baseline has been set for the project.
 
Use the following procedure to create a new resource forecast version using 
the Project Resource Forecast or the
Project Resource Forecasts window:
	- Open the Project Resource Forecast or the Project Resource Forecasts 
	window.
- Create a new record and enter a forecast type.
- Enter the project ID.
- Enter a description for the forecast version. The rest of the 
	information can be registered either now or later. 
- Save the record.