Connect Document Package to Activity
Explanation
By connecting a document package to an activity, the progress on the document package
will be reported to the activity. See 
Document Package in Document 
Management for
information on how the weighted progress is calculated.
Prerequisites
  - A document package must exist.
- An activity must exist.
System Effects
  - At any event that change any hours or progress, the progress from the documents connected to the
    document package is calculated into a weighted progress for the document package and
    reported to the activity.
Window
Project 
navigator/Connections
Activity/Connections
Related Window Descriptions
Project Navigator/Connections
Procedure
  - Select the activity to which you want to connect the document package, and select the 
	Connections
    tab.
- Click the menu option  Connect/ Disconnect Object.
- A new window appears. Select the 
	 Document Package tab.
- Select a document package from the list in the table. (Only document packages that are
    not already connected to an activity are listed in the table.)
- Click OK  to save the connection and close the dialog box.