Explanation
Perform this activity to set the selected project activity to the 
Completed status. Completing an activity means that no new work can be 
started, but the work you have already started can be completed. Once an 
activity is in the Completed status, it can be promoted to Closed status 
or be reopened into Released status. 
Prerequisites
  - The activity should be in the Released status.
System Effects
  - The activity is in the Completed status.
- No new costs, revenue or hours can be reported on the activity. Costs 
	already confirmed can be completed, e.g. transactions related to hours 
	reported can be transferred to Finance.
- The completed date is set to the current date.
Window
Activities
Project Navigator/Activity List
Project Navigator/Activity
Related Window Descriptions
Activities
Project Navigator/Activity List
Project Navigator/Activity
Procedure
	- Open the Activities window and query for the 
required activity that needs to be completed. 
- Right-click and click Complete in the menu.