Close Activity
Explanation
Perform this activity to set the selected project activity to the Closed 
status. Once an activity is in Closed status, it can only be demoted to 
the 
Completed status. 
The Actual Finish date is set to the Early Finish date if Actual Finish has 
not been set manually. 
Note: You are able to to check for any incomplete work on the activity before 
closing the activity. This is done in the Unfinished Activity Work 
window.
Prerequisites
  - The activity should be in either Released or Completed status.
- All work needs to be completed on the activity. 
 Refer to the activity 
Generate Unfinished Activity Work Items to get more information on the work that needs to be finished to be able to close the activity.
System Effects
  - The activity 
  is in the Closed status.
- No more cost,
	revenue or hours can be registered on the activity.
- Vouchers 
  cannot be created from any related 
  transactions.
- The closed 
	date is set to the current date.
- 
	If the activity belongs to a project PNG, it will be 
	removed from the PNG and will no longer appear in the 
	PPSAs Within PNG
	tab.
- 
	Actual Finish date is set to Early Finish if Actual Finish has not been set 
	manually.
Window
Activities
Project Navigator/Activity List
Project Navigator/Activity
Unfinished Activity Work
Related Window Descriptions
Activities
Project Navigator/Activity List
Project Navigator/Activity
Unfinished Activity Work
Procedure
	- Open the Activities window and query for the 
required activity that needs to be closed. You can perform this activity in the Project Navigator/Activity List 
	or the Project Navigator/Activity 
	tab as well.
- Right-click and then click the Close menu option.