Issue,Unissue and Manual Issue

In IEE client within Project Deliverables, it is not possible to issue items. For this functionality you should use the Aurena User Interface instead.

Within Aurena please go to the pages Project Deliverables Design or Project Delivables Materials and Services.

Explanation

This activity is used to issue top most material item/s of the deliverables structure. User needs to mark an issuable item using the Consumption Item toggle. Only the top most material item which have no any shipment plan or work task plan attached can be marked as a Consumption Item
Issue and Manually Issue commands will be available when the item is marked as consumption item and material is in Fully Received or Partially Received statuses. Material status will not be considered for the standard planned items. Consumption Plan will be created when issuing an item for the first time . Item can not be marked as non-consumption item once the consumption plan is created for an item.(Consumption Item toggle will be non editable at this point).Project connection will be created for the consumption plan and used cost will be reported through that if the supply option of the item is MRP.
Unissue command will be available till item being completed for the partially or fully issued items.


Note : Solution will be available only in Aurena. In IEE client, in Project Deliverable Navigator->Planning Items tab and in Project Navigator->Activity node->Demand->Material Plans tab, consumption plan detail will be visible for the information purpose.