In IEE client within Project Deliverables, it is not possible to issue items. For this functionality you should use the Aurena User Interface instead.
Within Aurena please go to the pages Project Deliverables Design or Project Delivables Materials and Services.
This activity is used to issue top most material item/s of the deliverables
structure. User needs to mark an issuable item using the Consumption Item toggle. Only the top most
material item which have no any shipment plan or work task plan attached can be
marked as a Consumption Item.
Issue and Manually Issue commands will be
available when the item is marked as consumption item
and material is in Fully Received or Partially Received statuses. Material
status will not be considered for the standard planned
items. Consumption Plan will be created when issuing an item for the first time
. Item can not be marked as non-consumption item once the consumption plan is created for
an
item.(Consumption Item
toggle will be non editable at this point).Project connection will be created
for the consumption plan and used cost will be reported through that if the
supply option of the item is MRP.
Unissue command will be available till item being completed
for the partially or fully issued items.
Note : Solution
will be available only in Aurena. In IEE client, in Project Deliverable
Navigator->Planning Items tab and in
Project Navigator->Activity
node->Demand->Material Plans
tab, consumption plan detail will be visible for the information purpose.