Enter Payment Schedule
Explanation
A payment schedule will enable you to enter the down payments and retentions 
connected to a purchase order that is sent to a supplier. The payment schedule 
lines can be connected to the relevant invoice. The down payment can 
be amortized when the supplier sends the invoice.
Prerequisites
A purchase order part or no part line must exist.
System Effects
	- A payment schedule with down payments and retentions will be created.
- The payment schedule will be connected to the purchase order.
- Invoices will be connected to the payment schedule.
Window
Payment Schedule for Purchase Order
Related Window Descriptions
Payment Schedule for Purchase Order
Connect to Payment Schedule
Procedure
	- Open the Purchase Order window and query for the required purchase 
	order.
- Enter a part or no part line as required.
- Right-click on the header part of the window and then click Payment 
	Schedules. The Payment Schedule for Purchase Order 
	window appears.
- Enter a new record and define the down payment amount.
- Release the purchase order and then you will be able to release the down 
	payment line by selecting the Released check box for the line.
- You can now either choose to make a direct payment in advance (through a 
	payment window) or create an advance 
	invoice.
- To create an advance invoice, enter the relevant details on the Manual 
	Supplier Invoice window. Select the Advance Invoice 
	check box and enter the gross amount.
- Right-click, point to Purchasing, and then click 
	Connect to Payment Schedule to connect the invoice to the 
	payment schedule.
- The Connect to Payment Schedule dialog box appears. 
	Click New and enter the order number. You can use the List of Values 
	to select the appropriate number.
- The matched amount can be modified in the case where you do not want to 
	match the full amount of the down payment.
- Click OK to save the connection.
- You will be able to view the matched invoice line back in the lower 
	table of the Payment Schedule for Purchase Order window.
- Open the Mixed Payment window to enter the details to pay 
	the invoiced amount. Once the voucher is created, you will get an information 
	dialog box informing you of the payment.
- Once the goods are received and the final invoice for the delivery is 
	created, you will be able to match the invoice with the purchase order 
	receipt. 
- On the Supplier Invoice window, right-click, point to Purchasing 
	and then click Match with PO Receipt.
- In the Post from Purchase Order dialog box that appears, you 
	will see the order number selected. Click OK to match with the 
	purchase order 
	receipt.
- If you have specified a retention for the payment schedule, you will 
	need to match the retention line with the final invoice. Right-click on the 
	invoice, point to Purchasing, and then click Connect to Payment 
	Schedule to connect the invoice to the retention. line.
- Since the down payment line will need to be amortized with the final 
	invoice, right-click on the invoice window and then click Advance Invoice. 
- Select the relevant invoice to connect from the Advance Invoice 
	Reference dialog box. You can modify the amount to be amortized if 
	required.
- Save the invoice.
- In the Payment Schedule for Purchase Order 
	window you will see the planned, matched and amortized amounts as well 
	as the connected invoice lines.