Explanation
Use this activity to approve or revoke approval for a 
milestone/stage payment line connected to a purchase order line. 
Prerequisites
	- At least one milestone/stage payment line must be 
connected to a released purchase order line.
- It should only be possible to approve a stage 
	payment if the stage payment percentage for all stage payment lines on the 
	purchase order line is equal to 100%.
- There must be a stage payment that is defined as 
	the last one as it will trigger a reconciliation process when it is 
	approved.
-  	The payment method of the purchase order line must be set to Staged.
System Effects
The milestone/stage payment line will get approved or 
the approval will get revoked.
Window
Purchase Order
Purchase Order Lines
Milestone/Stage Payment for Purchase Order Lines
 
Related Window Descriptions
Milestone/Stage Payment - Purchase Order
Purchase Order
Purchase Order/Part Order Lines
Purchase Order/No Part Order Lines
Purchase Order Lines
Milestone/Stage Payment for Purchase 
Order Lines
Procedure
	- Open the Purchase Order window.
- On the  Part Order Lines  tab, select the required order line and right-click, point to Order Line 
	Details and then click Milestone/Stage Payment; or on the
	No 
	Part Order Lines tab, select the required order line, 
	right-click and then click Milestone/Stage Payment. The 
	
	Milestone/Stage Payment window will appear.
Note: This activity can also be done on the 
Purchase Order Lines or 
Milestone/Stage Payment for Purchase Order Lines windows.
	- If the purchase payment type for the order line is Staged, you can 
	select which line is the last stage payment by right-clicking and then 
	clicking Last Stage Payment.
- Select the milestone/stage payment line(s) you 
	wish to approve or revoke approval for.
- Right-click and then click Approve and then OK on the 
	message that appears to approve the line or click Revoke Approval to 
	cancel the approval.
Note: The Date Approved field is set to 
the system date (today's date). Before approving the last stage 
payment, the purchase order line has to be closed and all other milestone/stage 
payments have to be approved.