Update Top Level Date
Explanation
Use this activity to update the due date on the top DOP order to be 
equal to
the demand date on the DOP header. The start date on the top DOP order will also
be updated due to the lead-time of the part which is based on current routing and
the quantity. If the top DOP order has supply orders, you can specify whether or not 
the due date of the supply orders should be automatically adjusted.  
Prerequisites
This activity requires, that a DOP structure to be generated for a DOP header. 
System Effects
  - The due date and start date are updated on
the top DOP order.
- If any time alarms exist due to a date 
	mismatch, they will be resolved.
- The due date for the supply orders of the top DOP order 
	are automatically adjusted when specified. Otherwise a time alarm is generated 
	for the date mismatch between the DOP order and the supply order. 
  
Window
DOP Header
Related Window Descriptions
DOP Header
DOP Header/Detail
Procedure
  - Select the DOP ID for which you want to update the due date on the top DOP
    order.
- Right-click and then click Update Top Level Date.
- If pegged supplies exist for the DOP top 
	part, a message appears requesting whether an automatic update for 
	the supply should occur. 
	If you choose not to update the due date on the 
	pegged order, a time alarm will be generated.
- After updating the top level date, you can 
	propagate the date change all the way down the structure by using the Propagate 
	Date Upstream right mouse button option.