Set Up Alternate Component Substitution Sequence
Explanation
Use this activity to define the alternate components for a part. You can have
as many alternate components as you wish, but you must define the order in which
the alternate components should be used. When backflushing in Production
Schedule you can use them as first choice or as backup choice. This means you
can define the alternates to be used either before the primary component, after
the primary component, or as a last-resort choice, etc. In Shop Order, the usage
of alternate component is an active choice by the material planner.  
Prerequisites
The part for which you want to register alternate components must be registered in the
inventory part register. The part you want to use as an alternate component must be
registered in the inventory part register.
System Effects
As a result of this activity, the system uses the registered components in place of the
standard components in different structures. This causes the backflush process to use a
different set of components for a temporary period of time, for a certain quantity, or for
particular structures.
Window
Alternate Component
Related Window Descriptions
Alternate Component
Procedure
	- Open the 
	Alternate Component window and populate it.
- In the Part No list, select the primary component for which you 
	want to enter an alternate component.
- Click anywhere in the table and create a new record.
- In the Substitution Sequence field, specify the order in which 
	the alternate component is to be used.
- Connect an alternate component by entering its part number in the 
	Alternate Part field or by selecting a part number from the List of 
	Values. The List of Values shows all allowable alternate componentsthat is, 
	all components that have been entered as alternate components on the 
	Alternate 
	Parts tab of the 
	Part window. 
	Note: If you enter an alternate component that has not been established 
	as a substitute to the selected primary component, a message appears 
	informing you of that fact and asking you whether you want to continue. If 
	you click Yes, the system creates a record that connects this new 
	alternate component to the primary component on the 
	Alternate 
	Parts tab of the 
	Part window.
- As an alternative to step 5, right-click on the row and then click 
	Copy Alternate Parts. The 
	Copy Alternate 
	Parts dialog box appears. Click OK to retrieve all 
	alternate components allowed for the site and primary component shown in the 
	dialog box.
- In the Effective From field, enter the date from which the 
	alternate component is to be valid. The default value is today's date. You 
	can also specify the date to which the part is to be valid in the 
	Effective To field.
- In the Qty per Component field, enter the number of components 
	needed. The default value is 1.
- If you want to specify for which parent part this component can be used 
	as an alternate, enter the part number of the parent part in the Parent 
	Part field or select it from the List of Values.
- Repeat steps 3 through 9 for each additional alternate component you 
	want to enter for the primary component.
- Save the record.