Remove DOP Routing
Explanation
Use this activity to remove the routing revision and alternative for a DOP order.
This will include removing the records for work guidelines, DOP order
operations, and tools. If you release a DOP order for a manufactured part without a
specified routing, no operations
will be added to the shop order. 
Prerequisites
	- The DOP order must have a routing revision and an alternative.
- Pegged shop orders for the DOP order and the branch must have a status 
	of Planned, Released, or Reserved.
- Pegged purchase orders must not exist. 
    
System Effects
  - As a result of this activity, the routing revision, alternative, work
guidelines, DOP order operations, and tools will be removed from the
DOP order. 
-  The start date will be recalculated due to the due date and lead-time,
where the lead-time depends on the lot size and routing revision and alternative. 
-  When the DOP order is released, the operations of its 
supply shop orders will be adjusted. 
  
Window
DOP Header
DOP Order
Related Window Descriptions
DOP Header
DOP Order
DOP Header/Structure
DOP Order/Detail
Procedure
  - Select the DOP order for which to remove the routing revision and alternative.
- Right-click, point to Change DOP Structure/Routing and then click Remove Routing. A message appears 
	requesting you to confirm the removal.
- Click Yes to confirm.