Propagate Quantity Upstream
Explanation
This activity is used to propagate quantities upstream in a DOP
structure (to child levels). The quantities on lower levels in the DOP structure will change with respect to
the quantity on the DOP order on which you perform the command.
Prerequisites
This activity requires that the DOP Order has components. 
System Effects
As a result of this activity:
	- The quantities on the lower levels
in the DOP structure are changed. The new quantity of the lower levels are 
	calculated primarily from the actual quantity required of the pegged supply 
	orders. For any un-supplied quantity, the lower level quantity is calculated 
	as the Un-supplied Qty x Qty Per Assembly + Component Scrap. 
	Also the inventory part scrap factor is considered.
- If serial numbers
are reserved for a component DOP Order and the quantity decreases, the correct amount of
the serial numbers is unreserved. If there is an overflow of netted quantity for a DOP 
	Order after the propagation, this quantity is un-reserved. 
- The start date is
recalculated for the DOP Orders on lower levels due to due date and lead-time,
where the lead-time is depending on lot size and routing revision and alternative.
Window
DOP Header
DOP Order
DOP Orders
Related Window Descriptions
DOP Header
DOP Header/Structure
DOP Header/Tree Structure
DOP Order
DOP Order/Detail
DOP Order/Tree Structure
DOP Orders
Procedure
  - Select the DOP Order from which to start an upstream propagation
    of quantities.
- Right-click and point to 
	
	Propagate Date/Quantity,
	 then click
	
	Propagate Quantity Upstream.
From the graphical object structure (DOP Order/Tree Structure or 
DOP
Header/DOP Structure): 
  - Select the DOP Order from which to start an upstream propagation of
    quantities.
- Right-click on the selected DOP Order object, point to Propagate 
	Date/Quantity and then click 
	Propagate Quantity Upstream.
From the DOP Orders window:
	- The one or several DOP orders from which to start an upstream 
	propagation of quantities. Note that the DOP orders must belong to different 
	DOP ID's.
- Right-click and point to 
	
	Propagate Date/Quantity,
	 then click
	
	Propagate Quantity Upstream.