Net DOP Branch
Explanation
Use this activity to perform netting processes for the selected order and all its lower
orders. It is also possible to perform re-netting when the quantity of the structure
is changed after the release; you can also re-net after canceling netting relations.
Netting is performed in the following sequence: 
  - Inventory - parts available in stock are automatically reserved to 
	the DOP order
- DOP Sourced Supply Orders - excess quantities available on shop and 
	purchase orders with demand source DOP Order are pegged to the DOP 
	order. Only supply orders in status Planned, Released or Reserved
	with a due date equal to, or earlier than the DOP order due date are 
	considered. 
- Inventory Sourced Supply Orders - excess quantities available on 
	shop and purchase orders with demand source Invent Order are pegged 
	to the DOP order. Only supply orders in status Planned, Released or
	Reserved with a due date equal to, or earlier than the DOP order due 
	date are considered. 
For
DOP orders where the DOP header is connected to a project, and where the Create
Pegged option is set to Pegged Orders,  netting is allowed only from the
project inventory. If the Create Pegged option
 is set to No Pegged Orders,
netting is allowed only from standard inventory. 
For project connected DOP orders, netting is performed in the following
sequence:
  - Inventory - parts available in project inventory for the same 
	project activity are automatically reserved to the DOP order
- DOP Sourced Supply Orders - excess quantities available on shop and 
	purchase orders connected to the same project activity with demand source 
	DOP Order are pegged to the DOP order. Only supply orders in status 
	Planned, Released or Reserved with a due date equal to, or earlier 
	than the DOP order due date are considered. 
- Inventory Sourced Supply Orders - excess quantities available on 
	shop and purchase orders connected to the same project activity with demand 
	source Project Inventory are pegged to the DOP order. Only supply 
	orders in status Planned, Released or Reserved with a due date 
	equal to, or earlier than the DOP order due date are considered.
Prerequisites
This activity requires that:
	- The DOP order has the netting parameter set to Netting or Auto 
	Netting.
- The status of the DOP order is not Closed or 
	Cancelled.
- A supply order with a quantity available to peg and demand source Invent Order, or DOP 
	Order exists. If the DOP order is connected to a project activity, the demand 
	source can also be Project Inventory. If the DOP order is project connected, the supply order must be 
	connected to the same project activity, or not connected to any project 
	activity. The pre-posting of the supply order must match the pre-posting of 
	the DOP header, or have no pre-posting. The shop order material lines / purchase order supplier material lines 
	must match the DOP order components. 
	If the shop order material line is DOP supplied, the DOP order ID of the 
	shop order material line must match the DOP order ID on the corresponding 
	DOP order component line.
System Effects
As a result of this activity:
	- For DOP orders set to allow netting from inventory, available parts in 
	stock matching the DOP order requirements are reserved to the DOP order thus 
	reducing the demand quantity for which own supply orders needs to be 
	generated and the quantity required for lower level DOP orders.
- For DOP orders set to allow netting from DOP sourced supply orders, 
	quantities available to peg from shop and purchase orders matching the DOP 
	requirements are pegged to the DOP order thus reducing the quantity for 
	which own supply orders needs to be generated.
- For DOP order set to allow netting from inventory sourced supply orders, 
	quantities available to peg from shop and purchase orders matching the DOP 
	requirements are pegged to the DOP order thus reducing the quantity for 
	which own supply orders needs to be generated.
- If serial numbers are reserved for a DOP order and the DOP order's demand is reduced due
to netting, the number of the corresponding serial number will be unreserved. 
	
Window
DOP Header
DOP Order
Related Window Descriptions
DOP Header
DOP Header/Structure
DOP Order
DOP Order/Detail
Procedure
  - Open the DOP Header/Structure 
	or DOP Order window.
- Select the DOP order for the branch, to be used for netting.
- Right-click, point to Net and 
	then click 
	Branch. 
- A message appears inquiring whether you want to net the branch DOP header. 
	Click Yes to confirm.