Manually Peg Supply Order to DOP Order
Explanation
This activity is used to manually peg existing 
purchased orders or shop orders to the DOP order.
Prerequisites
	- The status of the DOP order must be either Unreleased, Released 
	or Started.
- The DOP order must not already be fully supplied.
- The supply order must have demand source Invent Order, or DOP 
	Order. If the DOP order is connected to a project activity the demand 
	source can also be Project Inventory.
- if the DOP order is project connected, the supply order must be 
	connected to the same project activity, or not connected to any project 
	activity.
- The supply order must have a quantity available to peg.
- The shop order material lines /purchase order supplier material lines 
	must match the DOP order components. If the shop order material line is DOP 
	supplied, the DOP order ID of the shop order material line must match the 
	corresponding DOP order ID on the DOP order component line.
System Effects
As a result of this activity, supply orders are 
pegged to the DOP order and the Demand Source of the supply order will be 
set 
to DOP Order. If the DOP order is connected to a project activity, the 
supply order will be connected to this project activity as well.
Window
DOP Header
DOP Order
Related Window Descriptions
DOP Header
DOP Header/Structure
DOP Order
DOP Order/Detail
Manual Pegging of DOP orders
Procedure
	- Select the DOP order you want to peg manually.
- Right-click and then click Manual Pegging.
- The 
	Manual Pegging of DOP Order window opens with the 
	available purchase orders or shop orders.
- Enter quantity you wish to peg from each order in the Pegged Qty 
	field.
- Save.