Generate Line Schedule
Explanation
Use this function to generate line schedules for a specific part and line. Line
schedules can also be generated via MRP, Master Scheduling, or manually by entering
individual schedule lines. By entering parameters for the schedule quantities and dates,
you can quickly generate a basic line schedule for the part.
Prerequisites
A production line with an assigned line calendar must be defined. The part must be
defined for the production line before a production schedule can be created. The part must
have schedule horizons defined. The part must be of one of the following part types:
Manufactured, Manufactured Recipe, Purchased, or Expense.   
System Effects
As a result of this activity, the system creates a line schedule based on the
parameters you specified.
Window
Production Schedule
by Line
 Production
Schedule by Line Part
Production Line
Management
Related Window Descriptions
Production Schedule by Line
Production Schedule by Line Part
Generate Line Schedule
Production Line Management
Production Line Management/Current 
Production Schedule
Procedure
From Production Schedule 
by Line or 
Production Line Management/Current Production Schedule window: 
  - Search for the manufactured line for which you wish 
	to generate a line schedule.
- Select Generate Line Schedule by using the right-click option.
- Select the manufactured part for which you wish to generate a line schedule in the 
	Part
    No field. Use the List of Values to select from available parts.
- Enter the date range desired to generate the schedule in the From Date
	and To Date
    fields.
- Specify the frequency in days the schedule quantity should
    be generated in the Frequency in Days field, if a frequency other than the default
    of 1 is desired.
- Enter the initial schedule quantity in the Starting Qty
	field. Enter a step quantity in the Step
    Qty field, if the schedule should increase or decrease through the date range. As an
    alternative, enter an ending quantity in the End Qty field and select the
	Calculate Step Quantity to calculate the step quantity.
- If the daily quantities are to be spread into multiple
    scheduled receipts within a single day, mark the Distribute Within Days
	check box. Select the time period for when to schedule the quantities in the 
	Distribution
    Method list. If the Within Periods is selected in the Distribution
    Method list, enter a value in the Frequency in Min field to divide the quantity proportionally into the number of periods in
    the day according to the number of working minutes.
- Mark the Replace Existing Schedule check box to
    replace all schedule records for the specified date range.
- Click OK to generate and view the new schedule.
- Optionally, add or modify the packing instruction 
	for generated line(s)
From 
Production Schedule by Line Part
window: 
  - Search for the manufactured part for which you wish 
	to generate a line schedule.
- Right-click and select Generate Line Schedule.
- Select the manufactured line for which you wish to generate a line schedule in the
    Production Line field. Use the List of Values to select from available production
    lines.
- Enter the date range desired to generate the schedule in the From Date and 
	To Date fields.
- Specify the frequency in days the schedule quantity should
    be generated in the Frequency in Days field, if a frequency other than the default
    of 1 is desired.
- Enter the initial schedule quantity in the Starting Qty
	field. Enter a step quantity in the Step
    Qty field, if the schedule should increase or decrease through the date range. As an
    alternative, enter an ending quantity in the End Qty field and select the
	Calculate Step Quantity to calculate the step quantity.
- If the daily quantities are to be spread into multiple
    scheduled receipts within a single day, mark the Distribute Within Days
	check box. Select the time period for when to schedule the quantities in the 
	Distribution
    Method list. If the Within Periods is selected in the Distribution
    Method list, enter a value in the Frequency in Min field to divide the quantity proportionally into the number of periods in
    the day according to the number of working minutes.
- Mark the Replace Existing Schedule check box to
    replace all schedule records for the specified date range.
- Click OK to generate and view the new schedule.
- Optionally, add or modify the packing instruction 
	for generated line(s)