Define Production Schedule by Line Manually
Explanation
Use this activity to view, modify, or create a new production schedule for a
production line. You can
create a complete set of schedule records for a line, or just enter a new schedule record
in an existing production schedule. 
Production line schedules are normally generated by Master Scheduling or MRP, but you
can also change them manually. You can create schedule quantities beyond the
schedule horizon or any point within the schedule or firm horizons. Schedules created
beyond the schedule horizon will, however, be removed in the next schedule iteration if they do not fall within the firm horizon. You might also want to
change the time information to the due dates coming from Master Scheduling and MRP
to more distinctly identify the production schedule. You can also choose to break down a
single schedule quantity for a due date into multiple records, each with a distinct time.
Prerequisites
This activity has the following prerequisites:
  - A production line with an assigned line calendar must be defined.
- The part(s) must be
defined for the production line before a production schedule can be created.
- The part(s) must
have schedule horizons defined.
- The part(s) must be of one of the following part types:
Manufactured, Manufactured Recipe, Purchased, or Expense.
System Effects
As a result of this activity:
  - A production schedule for the production line is created.
Window
Production
Schedule by Line
Production Line
Management
Related Window Descriptions
Production Schedule by Line
Production Line Management
Production Line Management/Current 
Production Schedule
Procedure
  - Open the Production Schedule by Line or 
  Production Line Management/Current Production Schedule window.
- Populate the window or query for the production line.
- Create a new record in the table.
- Specify the due date for the schedule in the Schedule Date 
	field.
- Enter the sequence number for the schedule in the Build Sequence 
	field. Default
    value is 999.
- In the Part No field, select the part number to be manufactured. 
	Use the List of Values to select from available parts. Description of the part will be displayed in the Part Description field.
- Enter the amount to manufacture in the Qty Scheduled
	field.
- Optionally, add the desired packing instruction in 
	the Packing Instruction ID field.
- Repeat steps 3-8 for each schedule record you want to create.
- Save the record.