Define Planned Netting Group
Explanation
This activity is used to define a planned netting group. A planned netting 
group (PNG) is a collection of project activities (PPSA). 
PNG is beneficial in the multi project material requirement planning (MPMRP) 
process as it allows you to plan material transfers for a group of project 
activities. The transfer process will be handled by material transfer 
requisition (MTR). To control the sequence in which the MPMRP reviews the 
available material from each PPSA within each PNG, a priority number is 
assigned. You can exclude certain parts from a specific PPSA. The excluded parts 
will not be considered in MPMRP calculation.
For a project, you can define a PNG using either 
the Planned Netting Group window or the 
Create Project 
Planned Netting Group dialog box. It can also be created automatically 
if the Create Project PNG Automatically check box 
in the PMRP Basic Data/PNG Default Settings tab is selected.
Note: It is not possible to connect a PPSA to more than one PNG within the 
same site. You can connect one PNG to another PNG. However both PNGs should be 
within the same site. 
Prerequisites
This activity has the following prerequisites:
	- To create a PNG, the planner must have access to 
	at least one site.
- To create a project PNG, the material allocation method needs to be Within Project.
System Effects
As a result of this activity 
	- A PNG will be created.
- The PPSAs will be connected to PNGs.
- It is possible to connect PNGs together.
- Within PNG In/Out check box controls the 
	part transfer between PPSAs within the same PNG. 
 Possible values are :
 Allowed Automatic: The transfer allowed with automatic MTR approval
 Allowed Manual: The transfer allowed. MTR should be approved 
	manually.
 Not Allowed: The transfer is not allowed.
 Note: If Allowed Manual is selected in the Within PNG Transfer list or 
	Between PNG Transfer list, each planner in granting PPSA and receiving PPSA 
	has to 
	approve the MTR before it is executed.
- Borrow/Payback check box determines the 
	transfer type.
 Possible values are: Not Required and Required. If it is Not Required, the 
	transfer type is Transfer. If it is Required, the transfer type is 
	Borrow or 
	Payback.
- Between PNG IN check box controls the 
	incoming part transfer from another PPSA in a different PNG.
- Between PNG OUT check box controls the 
	outgoing part transfer to another PPSA in different PNG.
Window
Planned Netting Group
Projects
Project Navigator
Project
Related Window Descriptions
Planned Netting Group
Planned Netting Group/PPSAs Within PNG
Planned Netting Group/Allowed Between PNG 
Transfers
Planned Netting Group/Excluded Parts
Planned Netting Group/Include 
Activities Automatically
Projects
Project 
Navigator
Project
Procedure
To define a PNG without a project connection:
	- Open the 
	Planned Netting Group 
	window.
- Create a new record.
- Enter appropriate values in the PNG and
	PNG Description fields.
- Enter the site for which you want to create the 
	PNG or select one from the List of Values.
- Enter the priority number in the Priority 
	field.
- In the Within PNG In/Out, Between PNG In,
	Between PNG Out and Borrow/Payback lists select appropriate 
	options.
- If you want to automatically execute MTR process, 
	select Automatic MTR check box. 
 Note: System will automatically execute MTR only if the supply source type 
	is Inventory.
- If you want to generate MTR for planning purposes only, select Generate MTR for Planning Only check box. (MTR will not be executed).
 Note: It is not possible to select both Automatic MTR and Generate 
	MTR for Planning Only check boxes at the same time.
- Save the 
	record.
- Click the 
	PPSAs within PNG tab.
- To connect a PPSA to a PNG, create a new record 
	and select a PPSA from the List of Values.
- Enter the priority number in the Priority 
	field.
- Save the record.
- Alternatively, you can click the Include 
	Activities Automatically tab and enter a project ID. All the 
	activities belonging to that project, except those that have been closed or 
	canceled, will be automatically entered in the 
	PPSAs Within PNG 
	tab.
- To connect two PNGs together click 
	Allowed 
	Between PNG Transfers tab and select New.
- In the PNG 
	field, enter the PNG you want to connect or select a PNG from the List of Values.
- Save the record.
- Alternatively, you can right-click and then click Add Project Activities 
	to PNG.
- In the Query Condition area, select appropriate ID to 
	limit the query.
- Click Populate.
- Select the activitiy you want to include and click Add. 
	If you want to include all queried activities you can click Add All.
- Click Ok to close the dialog .
- To exclude parts from a certain activity, click 
	Excluded Parts tab and create a new record.
- Select the activity and the part no which you want 
	to exclude from MPMRP calculation.
- Save the record.
To define a project PNG using the 
Planned Netting 
Group window:
	- Open the 
	Planned Netting Group 
	window and create a new record.
- Enter an identifier for the PNG and a description 
	in the PNG and PNG Description fields respectively.
- Enter the priority of the PNG in the Priority
	field.
- Enter the site for which you want to create the 
	PNG or select one from the List of Values.
- Select appropriate options in the Within PNG In/Out, Between PNG In,
	Between PNG Out and Borrow/Payback lists.
- If you want to automatically execute the MTR process, 
	select the Automatic MTR check box. 
 Note: An MTR will be automatically executed only if the supply source type 
	is Inventory.
- If you want to generate an MTR for planning purposes only, select 
	the 
	Generate MTR for Planning Only check box. (MTR will not be executed).
 Note: It is not possible to select both the Automatic MTR and Generate 
	MTR for Planning Only check boxes at the same time.
- Save the 
	record.
- Click the
	Include Activities Automatically tab and create a new record.
- Enter the 
	project ID in the Project ID field.
- Enter a 
	number in the Priority field. The priority assigned to activities in 
	the 
	PPSAs Within PNG tab will begin with the value entered in 
	this field.
- In the 
	header area, select the Project PNG check box.
- Enter a 
	value in the Project ID field.
- Save the 
	record.
To define a 
project PNG using the Create Project Planned Netting Group dialog 
box:
	- Open the Projects, 
	
	Project Navigator or 
	Projectwindow and query for 
	the project for which you want to create a PNG.
- If you are using the Projects
	or 
	Project 
	Navigator window, select the project, right-click, 
	point to Netting and then click Create Project PNG. If you are 
	using the 
	Projectwindow, you can right-click in the 
	header or 
	General tab, point to Netting and then click
	Create Project PNG. The Create Project Planned Netting Group
	dialog box will appear.
- The PNG ID is the same as the project ID, but you 
	may modify the PNG description and priority if necessary.
- Select appropriate options in the Within PNG In/Out and Borrow/Payback lists.
- If you want to automatically execute the MTR process, 
	select the Automatic MTR check box. 
 Note: An MTR will be automatically executed only if the supply source type 
	is Inventory.
- If you want to generate an MTR for planning purposes only, select 
	the 
	Generate MTR for Planning Only check box. (MTR will not be executed).
 Note: It is not possible to select both the Automatic MTR and Generate 
	MTR for Planning Only check boxes at the same time.
- Click OK.