Define PNG Default Settings
Explanation
This activity is used to enter the default settings for 
a project planned netting group (PNG). These default settings will be used when 
a project PNG is created either automatically or by using the Create Project 
PNG right mouse button option from the 
Project 
Navigator window. You may modify these values for a PNG at any time.
Prerequisites
N/A
System Effects
These settings will be used by default when a new 
project PNG is created.
Window
Project MRP Basic Data
Related Window Descriptions
Project MRP Basic Data
Project MRP Basic Data/PNG Default Settings
Procedure
	- Open the Project MRP Basic Data window 
	and click the PNG Default Settings tab.
- To automatically create a PNG for a project, select the Create Project PNG Automatically
	check box.
- Select the Automatic MTR check box if you 
	want to allow a material transfer requisition (MTR) with the 
	Inventory 
	supply source to be executed automatically during the multi project MRP 
	process.
- To generate all MTRs with the 
	Planning transfer type, select the Generate MTR for Planning Only check box.
- Select a value in the Within PNG In/Out 
	list to indicate how part transfers between activities must be controlled.
- Select a value in the corresponding 
	Borrow/Payback list to indicate the borrow and payback requirements of 
	activities within the same PNG.
- Select a value in the Between PNG In list 
	to indicate how incoming part transfers from activities outside a PNG 
	should be controlled.
- Select a value in the Between PNG Out list 
	to indicate how outgoing part transfers to activities outside a PNG should 
	be controlled.
- Select a value in the corresponding 
	Borrow/Payback list to indicate the borrow and payback requirements of 
	activities which belong to different PNGs.
- Save the information.