Connect DOP Header to Project Activity
Explanation
Use this menu choice to connect a DOP Header to an activity after the DOP Header 
has been created. 
Prerequisites
	- Only DOP Headers in status Created can be connected to an activity.
- The DOP Header can not be connected to several activities - it's only possible 
	to connect a DOP Header to one activity.
- The project to connect to must be in status Approved or Started.
- The project activity must have status Planned or Released to be available.
- The site of the DOP Header must be defined as an allowed site for the connected 
	project.
- It shouldn't be possible to connect a DOP Header that's connected/created 
	as a job (attribute Financial Integration should be No Integration), against 
	an activity.
- The project code part may not already be preposted with a financial project.
System Effects
	- The DOP Header will be marked with the connected project/activity.
- 
	Pre-posting will be inherited from the project. As the dop header already exists, it may already have pre-postings. If pre-posting on the code part already exists, they will be replaced by the project pre-posting. If the project pre-posting has no value for a code part then the existing pre-posting on the object will remain unchanged. Also the project and activity sequence will be posted.
	
	
- The DOP Header appears as a connection in the Project Info/Connections-form.
- The DOP Header will return committed and used cost/hours and/or progress 
	when the connected activity runs the Refresh Activity Calculation.
- If the DOP Header start date and finish date is outside the start date and 
	finish date for the activity, a warning message is given.
Window
DOP Header
DOP Headers
Related Window Descriptions
DOP Header
DOP Headers
Procedure
	- Select the desired DOP Header that you wish to connect to a Project Activity
- Right click, point to Project Connection and then click 
	Connect to Activity.
- In the dialog box that pops up, select the Project Activity that you wish 
	to connect to.
- Click OK.