Highlight Options
Explanation
The Highlight options are used to highlight work orders, PM 
action occurrences or resources based on the selected options. There are five 
highlight options:
	- Highlight This
- Highlight These
- Highlight Critical work 
- Highlight Obstructive work
- Highlight affected Maintenance Work
Prerequisites
	- Maintenance Planning Board should should be opened.
System Effects
	- Highlight This: Selected Object will be highlighted.
- Highlight These: Selected Object and underlying objects will be 
	highlighted.
- Highlight Critical work: Work order and  work tasks and/or PM 
	Action which are defined as critical 
	work gets highlighted 
- Highlight Obstructive work: Work 
	task and/or PM work list that are scheduling obstructive will be highlighted.  
	 
	
- Highlight affected Maintenance Work: Scheduling 
	obstructive work tasks/work lists are highlighted if the Work Task/PM is scheduled later than the 
	planned finish date of the operational plan item and the earliest  
	start date of the work task/PM action occurrence is earlier than planned 
	finish date of the operational plan item. This means that the orders that 
	gets highlighted have the 
	possibility to be scheduled during the operational plan item if it becomes a 
	Maintenance window in Manual Plan/Operational plan window.
Window
Maintenance Planning Board 
Maintenance Planning Board for Planning Network
Related Window Descriptions
Maintenance Planning Board Client 
Procedure
Highlight This
	- Right Click on Navigator Items/Objects or Items/Objects in Gantt window 
	or Show dialogs
- Click Highlight This
Highlight These
	- Right Click on Navigator Items/Objects or Items/Objects in Gantt window 
	or Show dialogs
- Click Highlight These
Highlight Critical work 
	- Right Click on Navigator Items/Objects or Items/Objects in Gantt window 
	or Show dialogs
- Click Highlight Critical Work
 Note: This option is only available 
on Item/Object nodes that contains a work order/PM with Critical work
Highlight Obstructive work
	- Right Click on Navigator Items/Objects or Items/Objects in Gantt window 
	or Show dialogs
- Click Highlight Obstructive work
 Note: This option is only available on Item/Object nodes that contains a 
work order/PM with scheduling obstructive work tasks.
Highlight affected Maintenance Work
	- Right Click on Navigator Items/Objects or Items/Objects in Gantt window 
	or Show dialogs
- Click Highlight Obstructive work
 Note: This option is only available on Operational plan 
items that contains a work order/PM which is affected by the 
operational plan items.