Set Structure Component as Lot/Batch Origin
Explanation
Use this activity to set a connection between a parent 
part and one of its components.
Prerequisites
	- A structure alternate in 
	tentative status must exist.
- To inherit the Lot/Batch number, the Lot/Batch Tracking list must be 
	set to Lot Tracking for the parent part in  Part/General 
	tab.
- To be used in Production Schedule backflush method 
	Immediate must be selected.
- To be used in Production Schedule reporting points 
	cannot be used at the same time. 
System Effects
As a result of this activity the parent part will inherit 
the lot/batch number from the component with check box Lot/Batch Origin 
selected. Reserve and issue could only be done from one lot only 
(for the selected component)
Note: When selecting the Lot/Batch Origin 
check box, Expiration Date Origin check box will automatically be selected for 
that component.
Note: This value will be inherited to 
the order, where it will be editable.
Window
Product Structure
 
Recipe Structure
Related Window Descriptions
Product Structure
Recipe Structure
Procedure
	- Display the parent part for which you want to name a 
	lot/batch origin component, by populating or by making a selective query in 
	the Product Structure or Recipe 
	Structure window.
- Select the Lot/Batch Origin check box on the row of 
	the component you want the inheritance from.
- Save the record (F12).
- To be able to plan or use the structure, 
	right-click in the structure alternate section and then click either 
	Plan 
	or Build.