Distribute Cumulative Forecast
Explanation
This activity is used to distribute the cumulative 
forecast of an MS level 0 or MS level 1 part.
Prerequisites
MS set should be defined for selected MS level 0 or 
MS level 1 part. 
System Effects
As a result of this activity, the system creates forecast lines for 
the selected 
date interval.
Window
MS Level 0 Part
MS Level 1 Part
Related Window Descriptions
Distribute Cumulative Forecast
MS Level 0 Part
MS Level 1 Part
Procedure
  - Right-click on the MS Level 0 Part/Register Forecast tab or
  MS Level 1 Part/Register Forecast tab and then click 
  Distribute Cumulative Forecast.
- Enter values in the 
  From Date and
  To  
  Date fields.
- Enter value in the Cumulative Forecast field.
- Select forecast distribution method Daily, Weekly or 
	Monthly. 
- Select Calendar ID using List of Values.
- Click OK.