Transfer Demand to Purchase Requisition
Explanation
This activity is used to transfer an existing demand 
from a shop order requisition to a purchase requisition. This may occur when the 
parts to be manufactured before, are now to be purchased instead.
Prerequisites
	- A shop order requisition must exist.
- A purchase part must exist for the manufactured 
	part.
- The shop order requisition must not be connected to a project activity.
- The shop order requisition must not have been created from 
	Production Line Management.
- Serial and/or lot/batch numbers must not have been reserved to the shop 
	order requisition.
System Effects
	- A purchase requisition is created with the 
	relevant information.
- The quantity transferred to the purchase 
	requisition will be reduced from the shop order requisition. If the entire 
	quantity is to be purchased, the shop order requisition will be removed.
Window
Shop Order 
Requisition
Related Window Descriptions
Transfer Demand to Purchase 
Requisition
Shop Order Requisition
Shop Order Requisition/Detail
Related Visualization Chart Descriptions
Machine Operation Load In Standard Hours
Labor Operation Load In Standard Hours
Procedure
To transfer demand to purchase requisition using the data view:
	- Open the 
	Shop Order Requisition 
	window and query for the record you wish to transfer.
- Right-click on the header, or the 
	Detail 
	tab, and then click Transfer Demand to Purchase Requisition.
- On the dialog box that appears, enter the quantity 
	you wish to transfer in the Qty to Transfer field. The quantity cannot exceed the 
	current quantity on the shop order requisition.
- If required, change the requisitioner in the Requisitioner ID 
	field. This may be 
	required, for example, to prevent automatic removal of the created purchase 
	requisition when the next MRP is being run. 
- Click OK.
- A message appears stating the purchase 
	requisition number created. Click Yes to view it immediately.
To transfer demand to purchase requisition using the visualizer view:
	- Open a visualizer enabled window 
	and query for the site needed.
- If the Data View is displayed, click 
	Visualization View on the title bar. 
	
- Right-click and click 
	Select Visualization. 
	The 
	Select Visualization dialog box is 
	opened.
- Double-click 
	Machine Operation Load in Standard Hours 
	or 
	Labor Operation Load in Standard Hours.
- Select the bar/segment 
	representing the shop order requisition whose demand you want to transfer to 
	a purchase requisition, right-click
	and then click Transfer Demand to Purchase Requisition. The
	Transfer Demand to Purchase Requisition dialog box appears.
- Enter the quantity 
	you wish to transfer in the Qty to Transfer field. The quantity cannot exceed the 
	current quantity on the shop order requisition.
- If required, enter/change the requisitioner in the Requisitioner ID
	field. This may be 
	required, for example, to prevent automatic removal of the created purchase 
	requisition when the next MRP is being run. 
- Click OK.
- A message appears stating the purchase 
	requisition number created. Click Yes to view it immediately.
Note: The shop order requisition load will not be updated until the 
Capacity Requirements Planning (CRP) calculation has been executed.