Specify Scheduling Settings for Advanced Planning Board
Explanation
This activity is used to define the different default time frames used by the 
Advanced Planning Board (APB) when scheduling operations for a site. You also 
need to define how the APB should assign load to the different resources.
By specifying a transport calendar you can exclude non-working days when 
calculating the transport time. The transportation calendar takes effect only 
when shop order operations are scheduled and when the preceding operation or 
operations have a defined transportation time.
Prerequisites
This activity requires that the Advanced Planning Board must be enabled for 
the 
site.
System Effects
As a result of this activity, the values you specify are used by the Advanced 
Planning Board to schedule operations.
Window
Scheduling Basic Data
Related Window Descriptions
Scheduling Basic Data
Scheduling 
Basic Data/Shop Order Scheduling/General
Procedure
	- Open the 
	Scheduling Basic Data window and query for 
	the site you want to specify scheduling settings
	for.
- Click the Shop Order Scheduling/General 
	tab.
- Make sure that the Enable Constraint Based 
	Scheduling check box and the Use Advanced Planning Board option 
	are selected
- In the Scheduling Horizon field, enter the number of days that 
	the APB should consider when scheduling. The default value is 365. You can set any value up 
	to five years but shorter time frames will provide better performance.
- In the Scheduling Start Point (Hours from Present Time) field, 
	enter a default start time for the first operation in the schedule. This 
	optional value is set to 8 by default.
- In the Priority Adjustment Factor Weight field, enter a value to 
	indicate the weight used for prioritization of shop orders. The default 
	value is 1.
- In the Transport Calendar field, enter the calendar that you want 
	to use or select one from the List of Values. This calendar will be used to 
		calculate the scheduled transport time. When scheduling a shop order 
		operation, the scheduled transport time will be used.
 Note: To view 
		the transport calendar in the Advanced Planning Board, click Schedule Settings 
	on the Settings menu. The Schedule Settings 
		window opens. To view details of the transport calendar, double-click  
		the transport calendar object. For a graphical representation of the 
		transport calendar, drag the transport calendar object to object table 
	area.
 To view the scheduled transport time of a single shop order operation, 
		select the shop order operation object, right-click and then click Show. 
		The 
	Operations window appears. Click the Show
	Contents tab.
- In the Sequencing Horizon field, enter the 
	number of days to be used when sequencing orders. The default value is 10.
- In the Setup Optimization area, select one of the options to 
	determine what factors will be used by the APB to optimize setup.
- In the Adjust Schedule area, select the Allow Past Due Load in Adjust Schedule check box, 
    if you want to keep preceding operations of each of the reported/scrapped operations in the same operation structures in the past
     when the Adjust Schedule logic is executed. When the check box is not selected, the preceding operations of each of the 
     reported/scrapped operations in the same operation structures will be scheduled from current time.
- Save the information.