Sequence Shop Order Operations
Explanation
This activity is used to schedule shop order operations in sequence after 
each others from a given start date/time.
Prerequisites
	- Shop order operations must belong to the same work center.
- The status of the shop order operations cannot be Cancelled 
	or Closed.
- The Schedule Direction of the shop order operations 
	cannot be Manual Scheduling.
- The site should not use constraint based scheduling server.
- To create operation blocks, two or more of the operations cannot belong 
	to the same shop order.
- To base the sequencing order on characteristic code(s), they must have 
	been entered in Work Center/Characteristics tab.
- To automatically default the characteristic code(s) to use for 
	sequencing, the Sequencing Priority field should have a 
	value for the characteristic code(s) in Work 
	Center/Characteristics tab.
- To use the setup matrix, the Enable Setup Matrix must be 
	On in Work 
	Center/Characteristics tab for at least one of the 
	characteristic codes entered in Characteristics for Sequence Order 
	list.
- An operation cannot have a lower operation priority value relative 
	another included operation from the same order with lower operation sequence 
	number. I.e., operation priority cannot be used to change the order of the 
	operations within an order.
System Effects
	- The Schedule Direction for the included operations will 
	be set to Forward Scheduling and scheduled sequentially of 
	each others with the first operation starting on the start date/time 
	provided in the dialog box. Operations will be ordered following below 
	priority:
	-  Priority and Sort 
	Order defined in the Characteristics for Sequence Order 
	list. 
-  Operation Priority defined in
	Operations to Sequence list. Operations with a lower value 
	are scheduled before operations with a higher value.
-  Operation original Planned Start 
	Date/Time. Operations with an earlier original planned start 
	date/time are scheduled before operations with a later start date/time.
	- The preferred resource selected in the assistant will be set as the 
	preferred resource for the operations. If this work center resource is 
	available, operations will be scheduled on it.
- Operations parallel to, and succeeding the rescheduled operations will 
	also be set to Forward Scheduling and rescheduled.
- If Compress Operations is On, 
	and the new date/time for the rescheduled operation is later than the 
	original date/time, operations on the same shop order preceding the 
	rescheduled operation will be set to Backwards Scheduling 
	and rescheduled with a Finish Date adjacent to the 
	rescheduled operations new Start Date.
- If Setup Matrix is On, all 
	except the first operation will be scheduled with a setup time fetched from 
	the Work Center/Characteristics tab considering 
	the combinations for the characteristic codes entered in the 
	Characteristics for Sequence Order list. If several characteristic 
	codes have a setup matrix defined, the longest setup time will be used. 
- If Create Operation Blocks is On, 
	an operation block will be created and connected to all operations sharing 
	the same characteristic values for the characteristic codes entered in the
	Characteristics for Sequence Order list. If no 
	characteristic codes have been entered, or the operations does not have any 
	value for them, an operation block will be created and connected to all 
	those operations.
- If any of the operations are already connected to an operation block, 
	they will be disconnected from it. If this leaves the block with no 
	operations connected to it, the block will be deleted. 
Pages
Visual Shop Order Operations Planning
Shop Order Operations
Shop Floor Workbench
Procedure
This activity can be performed from the IFS Aurena client only. 
From Visual Shop Order Operations Planning page:
	- In the Machine Operations Scheduling chart, click the 
	resource card and then click Sequence. The 
	Sequence Shop Order Operations assistant appears.
- For operations you want to sequence, set Include to On and click 
	Next.
- In the Characteristics for Sequencing Order list, enter 
	the characteristic codes you want to base the sequencing order on.
 If a
	Sequencing Priority has been set for any characteristic 
	codes in the Work Center/Characteristics tab, 
	those will be appear automatically.
- In the Preferred Resource field, select the resource on 
	which you want the operations to be scheduled. Use the List of Values to 
	select from available work center resources.
- In the Start Date/Time field, enter the date and time 
	on which you want the first operation to be scheduled to start.
- If you want to avoid slack between operations preceding the sequenced 
	operation on the same shop order when rescheduled to a later date/time, set
	Compress Operations to On. 
- If you want to schedule setup according to the characteristic value 
	combinations, set Use Setup Matrix to On.
	
- If you want operation blocks to be created and connected to operations 
	sharing the same characteristic value, set Create Operation Blocks
	to On.
From Shop Floor Workbench and Shop 
Order Operations pages:
	- Search and select the operations you want to sequence.
- Click Scheduling, then click Sequence. 
	The Sequence Shop Order Operations assistant 
	appears.
- Follow above procedure from step 2.