Production Scrap
 
Explanation
 
This activity is used to declare scrap that occurred on the 
produced parts during the manufacturing process. For catch unit enabled parts, 
if the parent part comprises of one or more catch unit (CU) enabled components, 
the CU enabled components have to be reserved before backflush is performed.
Note: Labor and operation setup time for each receipt is calculated as;
 
[(setup time/standard lot size)*receipt quantity]
If standard lot size is not defined, then the total setup time will be reported 
for every receipt. 
 
Prerequisites
 
- This activity requires that a production schedule exists.
- The structure alternate cannot be a rework alternate.
System Effects
 
	- As a result of this activity, the system reports scrap for the parent 
	part and runs the backflush process to consume the components. The user 
	specifies whether the backflush process is run directly or in the 
	background. 
- If inbound locations are defined, they are used by backflush in its 
	search hierarchy. 
- If an alternate component substitution sequence is defined, it is used 
	by backflush when issuing material. 
- If making a scheduled receipt, the system automatically
updates the production schedule. If making an unscheduled receipt, the system does not
automatically update the production schedule.
- Inventory transactions are created for the scrap receipt and all issued 
	components. 
- Operation history transactions are created for any backflushed machine 
	or labor operations. 
- If CU enabled component parts exist in the schedule, a message will 
	appear informing you of the CU enabled component parts in the schedule.  
Window
 
Production Receipt 
Production Schedule by Line 
Production Schedule by Line Part
Production Line
Management
 
Related Window Descriptions
 
Production Receipt 
Production Schedule by Line
Production Schedule by Line Part
Production Line Management
Production Line Management/Current Production Schedule
Scrap Receipt
 
Procedure
 
From the  
 
Production Receipt 
window: 
 
  - Open the 
	Production Schedule window. 
	 
	
- In the
	 Production Line
	 list, 
	select the production line and part for which to report scrap.
- Right-click and then click 
	 
	Scrap Receipt. The 
	  Scrap 
	Receipt 
  
	dialog box appears.
- In the 
	 Scrap Receipt 
	dialog box, Select the Receipt in Background check box to execute the receipt in the background  
	 .
- In the Sched Option list, select Scheduled 
  to consume from the quantity scheduled, or Unscheduled to not 
  consume from the scheduled quantity.
- In the  
	Structure 
  area, specify the structure revision and structure alternate. If desired, also 
	specify the routing revision and the routing alternate.
- In the 
	  Production Scrap
	 area, 
	type the quantity scrapped in the 
	Qty Scrapped field. Click in the Scrap Reasons field, then 
	click   
	List
	 to select from available scrap 
	reasons. If the part is catch unit enabled, the catch quantity should also 
	be entered.  
  
 
- In the
	 Report Point
	 area, 
	select the  
	Complete Scrap
	 check box to specify 
	that this is the complete scrap for the manufacturing process.
- Click  
	OK.
From the Production Schedule by Line or Production 
Line Management/Current Production Schedule window:
    - Search for the production line.
- Select the production schedule 
  line for which you want to 
	report scrap. Right-click and then click 
	 
	Scrap Receipt. The 
	 
  Scrap Receipt 
  
	dialog box appears.
- In the 
	 Scrap Receipt 
	dialog box, Select the Receipt in Background check box to execute the receipt in the background  
	
- In the Sched Option list, select Scheduled 
  to consume from the quantity scheduled, or Unscheduled to not 
  consume from the scheduled quantity.
- In the 
	  Structure
	 area, specify 
	the structure revision and structure alternate. If desired, also specify the 
	routing revision and the routing alternate.
- In the
	 Production Scrap
	 area, 
	type the quantity scrapped in the 
	Qty Scrapped field. Click in the Scrap Reasons field, then 
	click   
	List
	 to select from available scrap 
	reasons. If the part is catch unit enabled, the catch quantity should also 
	be entered in the Catch Qty Scrapped 
	field.   
  
 
- In the  
	Report Point 
  area, select the 
	 
	Complete Scrap check 
	box to specify that this is the complete scrap for the manufacturing 
	process.
- Click
	 OK.
From the 
Production Schedule by Line Part window: 
 
 
  - Search for the part.
- Select the production schedule 
  line for which you want to report scrap. Right-click and then click 
	 
	Scrap Receipt. The 
	 
  Scrap Receipt 
  
	dialog box appears.
- In the 
	 Scrap Receipt 
	dialog box, Select the Receipt in Background check box to execute the receipt in the background 
   .
- In the Sched Option list, select Scheduled 
  to consume from the quantity scheduled, or Unscheduled to not 
  consume from the scheduled quantity.
- In the 
	  Structure
	 area, specify 
	the structure revision and structure alternate. If desired, also specify the 
	routing revision and the routing alternate.
- In the 
	  Production Scrap
	 area, 
	type the quantity scrapped in the Qty Scrapped field. Click in the 
	Scrap Reasons field, then click
	 
	List
	 to select from available scrap 
	reasons. If the part is catch unit enabled, the catch quantity should also 
	be entered in the Catch Qty Scrapped 
	field.  
  
 
- In the
	 Report Point
	 area, 
	select the 
	 
	Complete Scrap check 
	box to specify that this is the complete scrap for the manufacturing 
	process.
- Click  
	OK.