Perform Report Point Receipt with Catch Unit Components   
Explanation
This activity is used to handle report point receipt of Catch Unit (CU) enabled 
component parts in the production schedules. A catch unit is enabled to allow a specific
inventory part to manage two parallel units of measure. Information regarding 
both quantities, inventory and catch, are saved on all the transaction history 
records.
Prerequisites
A part can be reserved as a catch quantity only if it
is catch unit enabled for the part.   
System Effects
	- As a result of this activity, the system will backflush 
the CU enabled components and operations used
up to the defined report point. 
- The 
report point balance will be updated for the specific report point. 
- If
routing is defined, all the operation steps falling between this report point and the previous 
one are backflushed at standard cost. 
- Operation-linked catch
unit enabled components used by the reported operations
will be backflushed. 
- Material not linked to 
operations is assumed to be required at the start of the production. Thus, it is backflushed at the first report point. 
- If inbound locations are defined, they
will be used in the backflush search hierarchy.
- If an alternate component 
substitution sequence is defined, it will be used in backflush when issuing material. 
Inventory transactions will be created for all issued catch
unit enabled components. 
- History transactions are written for any backflushed machine or labor 
operations. 
Window
Report Point 
Receipt
Production 
Receipt
Production 
Schedule By Line 
Production Schedule By Line Part
Production Line
Management 
Related Window Descriptions
Report Point 
Receipt
Production 
Receipt
Production 
Schedule By Line
Production Schedule By Line Part
Production Line Management
Production Line Management/Current 
Production Schedule
Procedure
From the 
Report Point Receipt/Production Receipt window: 
  - Open the 
	Report Point Receipt/Production Receipt 
	window.
- In the 
	
	Production Line list, select the production line and part for 
	which to report production.
- In the 
	Structure area, specify the structure 
	revision and structure alternate. If desired, you can specify the routing 
	revision and the routing alternate.
- Select the Receipt in Background check box to execute the receipt in the background.
- In the 
	Qty Reported field, type the quantity to report at the specific report 
	point. You cannot report more quantities than were reported at a previous 
	report point.
- Select the Edit Components check box.
- 
  Save. 
	The 
	Production Receipt
    Material dialog box will appear.
- In the 
	Production Receipt Material 
	dialog box, type a value in the
    Qty To Issue field. 
- To change components, click 
	New. The cursor appears in the 
	Part To Issue field. Click  
	List 
	to select from available parts. Next, type a value in the Qty
    to Issue field.
- 
  Save.
- To reserve the components before backflushing, select the components, then click 
	Assign.
    The 
	Production Receipt Reservation dialog box will appear.
- In the 
	Production Receipt Reservation 
	dialog box, click 
	Create.
    The 
	Inventory Part Location dialog box will appear.
- In the 
	Inventory Part Location 
	dialog box, select a location.
    Click OK.
- In the 
	Production Receipt Reservation 
	dialog box, type a value in
    the Qty Assigned field. Save, then click  
	OK when the reservations
    are finished. Also enter the catch quantity that you want to reserve in the Catch Qty Assigned field.  
	
- When you are finished editing and reserving components, click  
	OK to run
    the backflush.
From the Production Schedule by Line or Production 
Line Management/Current Production Schedule window: 
 
  - Search for the production line for which you want to report production.
- Select the production schedule line for which to report.
	Right-click and then
    click Production Receipt. The 
	Production Receipt 
	dialog box will
    appear.
- In the 
	Production Receipt 
	dialog box, specify how many parts you
    want to report and receive into inventory in the Qty Reported field. The scheduled
    quantity is the default value.
- Select the Receipt in Background check box to execute the receipt in the background.
- In the Structure 
  area, specify the structure revision
    and structure alternate. If desired, you can specify the routing revision and the routing
    alternate.
- In the Location 
  area, select the 
	Report Point check box to create
    a report point receipt.
- In the Location 
  area, specify the report point in the 
	Report Point field. Click List to select from available report points.
- To edit components, click 
	Components. The 
	Production Receipt
    Material dialog box will appear.
- In the 
	Production Receipt Material 
	dialog box, type a value in the
    Qty To Issue field.
- To change components, click 
	New. The cursor appears in the 
	Part To Issue field. Click  
	List 
	to select from available parts. Next, type a value in Qty to
    Issue field.
- 
  Save.
- To reserve the components before backflushing, select the components, then click 
	Assign.
    The 
	Production Receipt Reservation dialog box will appear.
- In the 
	Production Receipt Reservation 
	dialog box, click 
	Create.
    The 
	Inventory Part Location dialog box will appear.
- In the 
	Inventory Part Location 
	dialog box, select a location.
    Click OK.
- In the 
	Production Receipt Reservation 
	dialog box, type a value in
    the Qty Assigned field. Save, then click 
	OK when the reservations
    are finished. Also enter the catch quantity that you want to reserve in the Catch Qty Assigned field.  
	
- When you are finished editing and reserving components, click  
	OK to run
    the backflush.
From the 
Production Schedule by Line Part 
window:
  - Search for the part for which to report production.
- Select the production schedule line for which to report production. 
  Right-click and then click Production Receipt. The 
	Production Receipt 
	dialog box will
    appear.
- In the 
	Production Receipt 
	dialog box, specify how many parts you
    want to report and receive into inventory in the Qty Reported field. The scheduled
    quantity is the default value.
- Select the Receipt in Background check box to execute the receipt in the background.
- In the Structure 
  area, specify the structure revision
    and structure alternate. If desired, you can specify the routing revision and the routing
    alternate.
- In the  
	Location 
  area, select the 
	 
	Report Point check box to create
    a report point receipt.
- In the  
	Location 
  area, specify the report point in the 
	Report Point field.
    Click List to select from available report points.
- To edit components, click 
	Components. The 
	Production Receipt
    Material dialog box will appear.
- In the 
	Production Receipt Material 
	dialog box, type a value in the
    Qty To Issue field.
- To change components, click 
	New. The cursor appears in the 
	Part To Issue
    column. Click List to select from available parts. Next, type a value in 
	Qty to
    Issue field.
- 
  Save.
- To reserve the components before backflushing, select the components, then click
	 Assign.
    The 
	Production Receipt Reservation dialog box will appear.
- In the 
	Production Receipt Reservation 
	dialog box, type a value in
    the Qty Assigned field. Also enter the catch quantity that you want 
	to reserve in the Catch Qty Assigned field.    
- 
    Save.
- When you are finished with editing and reserving components, click  
	  
	OK to
    run the backflush.