Modify Ongoing Operation
Explanation
This activity is used to register changes for an ongoing operation or a set of operations. 
I.e. adding/removing employee/team and starting/stopping machine/labor time.
Prerequisites
	- A production or setup activity must have been started on the operation.
- The Crew Size can only be modified if Reporting Mode has 
	been set to Anonymous Reporting on the used site.
- Employees can only be added and removed if Reporting Mode has 
	been set to Employee Reporting on the used site.
- If an employee qualification requirement 
	exists for the operation, and the qualification check for the site is 
	mandatory, then the reporting employee(s) must have those qualifications. 
System Effects
	- If the Machine Time check box is selected a new machine clocking 
	sequence will be created.
- If the Labor Time check box is selected a new labor clocking 
	sequence will be created.
- If an Employee is added a new labor clocking sequence will be created.
- If Machine Time check box is not selected, the machine clocking 
	sequence will be stopped and one operation history transaction will be 
	created per operation. (For more information see Stop Production/Stop Setup 
	activities for details)
- If the Labor Time check box is not selected all active labor 
	clockings sequences will be stopped and one operation history transaction 
	will be created per employee and operation. (For more information see Stop 
	Production/ Stop Setup activities)
- If an Employee is removed this clocking sequence will be stopped and one 
	operation history transaction will be created per operation. (For more 
	information see Stop Production/Stop Setup activities).
- If the value in the Crew Size field is changed, the labor 
	clocking will be stopped and one operation history transaction will be 
	created per operation. A new labor clocking sequence will be created 
	carrying the new crew size value. (For more information see Stop Production/ 
	Stop Setup activities)
- If the Clocking Note is changed the new note will be saved on all 
	active clocking sequences.
- If the Resource is changed, the machine clocking will be stopped 
	and one operation history transaction will be created per operation. A new 
	machine clocking sequence will be created carrying the new resource value. 
	(See Stop Production/Stop Setup activities for details).
Window
Shop Floor Workbench
Related Window Descriptions
Shop Floor Workbench
Modify Ongoing Operation
Procedure
From Modify Operation dialog box:
	- In the Shop Floor Workbench window, select the operation and 
	click Modify Ong. Operation.
- The Modify Ongoing Operation dialog box will open.
- Update the parameters in the dialog to reflect the new situation.
- Click OK. The started and stopped clockings can be viewed from the 
	Clockings tab.