Create Purchase Order from Chart
Explanation
Use this activity to create a new purchase order for 
the part record selected in a chart.
Prerequisites
	- The part must not be configured.
- The part must not be connected to a project.
- The Part Type list should be set to either
	Purchased or Purchased (Raw) in the Inventory 
	Part/General window and a primary supplier must exist in the 
	Supplier for Purchase Part window.
- The requisitioner must have been entered on the 
	Requisitioners tab of the  
Procurement Basic Data window.
System Effects
As a result of this activity, the system creates a purchase order 
in Planned status and a purchase order line with Released status 
for the primary supplier and the specified date and quantity. The system automatically generates the 
order number. 
Window
N/A
Related Visualization Chart Descriptions
	Inventory Part Availability Planning
Related Window Descriptions
Create Supply from Visualizer
Procedure
	- Open a visualizer enabled window and query for the site needed.
- If the Data View is displayed, click Visualization View on the title bar. 	
	
- Right-click and select Select Visualization. 	The Select Visualization dialog box 
	appears.
- Double-click Inventory Part Availability Planning.
- Select one or several segment(s) representing the demand(s) you want to create a supply for.
- Right-click, point to  	Create Supply Order  and then click  Create 
	Purchase Order. The Create Purchase Order dialog box 
	appears.
	
- The sum of the demands for the selected 
	segment(s) appears by default in the Supply Quantity field, but can 
	be manually changed.
- The earliest due date from the selected demand(s) 
	appears by default in the Due Date field, but can be manually 
	changed.
- Click OK.