Create Multilevel Repair Shop Order
Explanation
This activity is used to create a new multilevel repair shop order for a 
specified part. 
Prerequisites
In order to create a multilevel repair shop order, the
Create Multilevel Repair Shop Orders field should be selected in 
Site/Extended Site Info/Manufacturing. The part to be repaired should be 
multilevel-tracked. 
In order to process a multilevel repair there are some 
additional requirements to be fulfilled:
- The parent part to be repaired should be multilevel-tracked 
and there should be at least one child existing for the parent part in the as-built structure. The parent parts should be 
completely reserved to the multilevel repair shop order.
- There should exist at least one buildable repair structure alternate for each of the structure levels to execute multilevel repair in that specific structure level.
- 
If there exist a lot tracked, but not serial tracked parent that consist of serial tracked components in the as-built structure, such 
parts will not be able to reserve to a multilevel repair shop order. This 
combination should not occur on any level of the as-built structure corresponds to the reserved parent part.
If the parent part is serial-tracking-enabled:
	- The quantity in the repair shop order should be 1.
- The parent part should not contain a structure underneath IFS/VIM.
Note: In case the parent part is both serial and lot/batch-tracked, the generation of 
as-built structure does not consider the lot/batch number of the reserved parent 
part. Here the as-built structure is generated by selecting the records with the 
highest as-built revision number for the same parent serial. This is required to 
get the latest as-built structure for a serial where the lot/batch number of the 
parent has been changed due to some reasons. 
If the parent part is not serial-tracked but lot-tracked,
	- All the parent parts should be reserved from a 
	single lot/batch.
System Effects
As a result of this activity the system creates a new multilevel repair shop 
order for the selected part. When this happens, the system creates material 
requirements for the parent part and any existing components the respective 
repair structure alternate as non-consumable materials. All the consumable 
components that exist in the repair structure alternate are excluded when 
creating a multilevel repair shop order.
Window
Shop Order
Shop Orders
Production Line Management
Related Window Descriptions
Shop Orders
Shop Order
Shop Order/Material
Shop Order/Operation 
Shop Order/Operation Tools
Shop Order/Detail
Production Line Management
Production Line Management/Shop Orders
Procedure
From the 
Shop Order window: 
  - Create a new record.
- Enter a value in the Order No field if you want. Otherwise, the 
	system assigns a value automatically.
- Enter the part number in the Part No field of the part that you 
	want to repair. Use 
  the List of Values to select from 
	available parts. A value appears automatically in the Description
  field. 
- Select Repair from the Structure Type 
	list.
- From the  Sched Direction list, 
	select either 
  Forward Scheduling or
    Backwards Scheduling.
- Enter either the earliest start date or the need date. The system 
	calculates the start and finish dates automatically based on routing 
	operations of the part.
- Enter the desired lot size that you want to repair. Here the lot size 
	should be 1 if the repair part is serial-tracked.
-  In the 
	Revision/Alternative
	area, enter new values in the Structure or Routing fields if 
	you want to use another structure or routing revision and/or alternative. 
	Use the  
  List of Values to select from available 
	values.
- Save your changes.
- In the 
	Operation tab, enter new operations 
	and/or labor operations or revise existing ones as necessary to match this 
	shop order.
- In the 
	Operation Tools tab, enter new operation 
	tools or revise existing ones as necessary to match this shop order.
- In the 
	Detail tab, enter information about the 
	closure of the shop order. This might include information about close 
	tolerance or whether the order should be closed manually or automatically.
From the Shop Orders 
and Production Line Management/Shop Orders windows: 
  - Create a new record.
- Enter a value in the Order No field if you want. Otherwise, the 
	system assigns a value automatically.
- Enter the part number in the Part No field of the part that you 
	want to repair. Use 
  the List of Values to select from 
	available parts. A value appears automatically in the Part Description 
  field.  
  
- Select a site. Use the List of Values 
	to choose from available sites.
- Select Repair from the Structure Type 
	list.
- In the Sched Direction field, select either 
  Forward Scheduling or 
   
  Backwards Scheduling.
- Enter either the earliest start date or the need date. The field in which 
	you make the entry depends on the value that you selected in the Sched 
	Direction 
  field. 
- Enter the desired lot size that you want to repair.
- Save your changes.
Note: Verify that multilevel repair is selected in the 
Shop 
Order/Detail tab.