Analyze Shop Order Material Availability
Explanation
Use this activity to analyze the component availability for a shop order. 
Planning part is only available for Company Owned Stock and Supplier Consignment 
Stock. The check can run automatically as well as manually. You can choose to run 
the manual check either for selected orders or for an entire site. It is useful 
to check material for the site at regular intervals since there may be material 
shortages caused by supply changes occurring after the last availability check.
Prerequisites
	- This activity requires the existence of a shop order.
- The shop order must be in Planned state if 
	you want to use the Run Availability Check right-click option.
System Effects
	- The system displays availability planning information in the 
	Inventory Part Availability Planning window.
- If you run the availability check manually, you 
	will see a message indicating any availability problems that exist. All 
	connected components will be considered during the check regardless of 
	whether or not they have the 
	Availability Check check box in 
	the 
	Inventory Part/Misc Part Info tab selected. The 
	details can be viewed in the Planning Alerts - 
	Shop Order 
	window.
- If you calculate planning alerts by site, you will 
	be able to see the results in the Planning Alerts 
	- Shop Order 
	window once the background job completes.
- In the case of manual checks, the Last 
	Availability Check field in the 
	Shop Orders
	window will be updated with the current date for each order included in the 
	check.
- The Planning Alert Exists check box in the
	Shop Orders window will be selected for the orders 
	which have shortages.
Window
Shop Order Availability
Shop Orders Material Planning
Shop Order
Shop Order Materials
Shop Orders
Inventory Part Availability Planning
Calculate Planning Alerts for Site
Planning Alerts - Shop Order
Production Line Management
Related Window Descriptions
Shop Order Availability
Shop Orders Material Planning
Shop Order
Shop Order/Materials
Shop Order Materials
Inventory Part 
Availability Planning
Shop Orders
Calculate Planning Alerts for Site
Planning Alerts - Shop Order
Production Line Management
Production Line Management/Shop Orders
Procedure
To analyze the availability for a single shop order:
  - Open the Shop Order Availability 
	window and search for the shop order whose availability you want to study. 
	
- To use the current date as a due date, select the Pick Plan Today check box in the 
	Query Conditions area. 
- To view non-reserved material lines, select the Only Show Required>0 check box. The lines with non-reserved material are displayed in the lower part of the window. 
	
- To view material lines with shortages, select the Only Show Shortages check box. The lines having a shortage of material are displayed in the lower part of the window. 
To analyze the availability for a set of shop 
orders:
	- Open the 
	Shop Orders Material Planning window and 
	search for the shop orders you want to study.
- In the Query Conditions for Components 
	area, select the Include Requisitions check box if you want the values 
	in the Projected Qty Onhand, Total Demand and Total Supply
	fields to consider open requisitions in addition to orders.
- Select the Remaining to Allocate > 0 check 
	box to display only the component lines for which there is material 
	remaining to be reserved or issued.
- Select the Only Show Shortages check box to 
	display only the component lines for which there is a material shortage, 
	i.e. components for which the projected quantity onhand on the required date 
	is less than zero.
- Enter a date in the Pick Plan Date field if 
	you want to use a different date instead of the Date Required when 
	calculating the Projected Qty Onhand, Total Demand and Total Supply.
- Click Refresh to retrieve the information according to the query conditions 
	you specified in steps 3 to 5.
- Select a shop order in the upper table of the 
	window to view its material planning information in the lower table.
To analyze the availability information for a shop order 
material line:
	- Select the material line for which you want to 
	view the availability planning in the Shop Order/Materials tab or Shop Order 
	Materials window.
- Right-click and then click 
  	Availability Planning. 
	The Inventory Part Availability Planning window appears. 
	This window shows the demand and receipts for the inventory part.
To run an availability check for selected shop orders 
in Planned state:
	- In the Shop Orders 
	or Production Line Management/Shop Orders window, 
	select the shop order(s) that you want to include in the check.
- Right-click and then click Run Availability 
	Check. The 
	Run Availability Check for Material dialog box 
	opens.
- In the Pick Plan Date field, you may enter 
	a date to be used as the required date for the order(s). If this field is 
	left blank, the material allocation dates on the shop orders will be used instead.
- Click OK. A message will be displayed to 
	indicate if any shortages were detected once the check is complete. You can 
	identify the orders for which there are shortages via the Planning Alert 
	Exists field and view further details via the Planning Alerts and
	Component Availability right-click options.
To calculate and analyze planning alerts by site:
	- Open the 
	Calculate Planning Alerts for Site
	dialog box.
- Your default site will appear in the Site 
	field. You may enter the short code for another site here or click List 
	to select one from a List of Values.
- Click OK. The calculation will be performed 
	as a background job.
- Open the Planning Alerts - Shop Order 
	window and search for the shop order to analyze the generated alerts.