Specify Maintenance Import Interval
Explanation
Use this activity to schedule the importation of work orders from 
IFS/Maintenance. These work orders are considered as resource breaks within 
Constraint Based Scheduling (CBS). Neither maintenance break dates and times nor break times can be 
modified.
Prerequisites 
This activity has the following prerequisites:
  - IFS/Maintenance must be installed.
-  Either a CBS site or an Advanced Planning Board (APB) site must be defined 
	and enabled in the 
	
	Scheduling Basic Data window.
The work orders that will be imported as resource 
breaks has to fulfill the following constraints:
  - The work order site should be the same site where the 
	import is done for.
-  The work order should be connected to a object 
	which represents a work center resource or a tool instance.
- The operational status on the work order should 
	be Obstructive.
-  Planned finish date on the work order has to be 
	defined and should be before the end of the scheduling horizon
- Planned start date on the work order has to be 
	defined and should be after the start of the scheduling horizon.
-  The work order status should be
	
	Under Preparation, Prepared, Released or Started.
- The execution time needs to be defined on the work 
	order.
System Effects
As a result of this activity:
  - The system deletes corresponding resource breaks for any closed or 
	canceled work orders when importing. 
-  The imported work orders are compared against the corresponding resource breaks. Any updated work orders will update the corresponding resource breaks 
	and the new work orders will create new resource breaks.
Window
Maintenance Import
Related Window Descriptions
Maintenance Import
Procedure
  - Open the 
	Maintenance Import 
	dialog box.
- Enter values in the Site, Work Center No,
	Resource ID, Begin Date Offset, and End Date Offset 
	fields according to the work orders that you want to import.
- Click Schedule and follow the steps in the 
	assistant.