Sorting
Explanation
This activity is used to manually sort object before scheduling.
This activity is performed for various reasons.
	- Option - Sort by Precedence : When it seems that 
	scheduling is not taking place as expected, the internal sorting of 
	operations might not have taken place. This manual sorting option would make 
	operations sort again and scheduling would happen as expected. 
- Options - Sort by , LPST, EDD, Work Order 
	Priority : When there are identical orders competing for same resources 
	thee user can select one of these sorting options and force scheduling logic 
	to give priority to certain orders based on the sort option.
Prerequisites
Sorting will effect only unscheduled operations/orders
System Effects
The internal sorting order of operations or orders will be re-ordered as per 
the sort by option.
Window
Scheduling Client
Simulation Client
Advanced Planning Board
Maintenance Planning Board
Maintenance Planning Board for Planning Network
Related Window Descriptions
Scheduling Client
Simulation Client
Advanced Planning Board
Maintenance Planning Board
Maintenance Planning Board for Planning Network
Procedure
	- In the Gantt chart, select the unscheduled orders/operations that you 
	want to sort.
- Select right mouse button menu option Sort by Precedence
	if you want to sort operations inside orders with their preceding, 
	succeeding relationships. - accordingly the operations will be sorted 
	internally. Execute any scheduling actions to see if desired results are 
	achieved after sorting.
- Select right-click option and select the sort option which you need as 
	the dispatch rule for your operations. Sort By LPST will sort 
	operations or orders according to their latest possible start time. Sort 
	by EDD will schedule orders according to their earliest due date. Sort 
	by Work Order priority will set work orders orders to sort according 
	to their work order priority.
- Once sorted , schedule orders to see if it gives the desired results. 
	for example , if you sorted orders Sort by EDD, and then if you 
	schedule orders As Soon As Possible then orders will schedule in the 
	priority order that the order having earliest due date will take the time 
	slot closest to current time. If any order happens to become tardy , then 
	those would be the once who is having later due date.