Reject Resource Breaks
Explanation
This activity is used to reject an Unscheduled 
resource break. The status of the break changes to Finished. A resource 
break in Finished state has no effect on the shop order schedule. Resource breaks 
in Unscheduled or Scheduled state are taken into account 
only when the orders are scheduled using Constraint Based Scheduling (CBS), not when using the Shop Order Infinite Scheduler. 
Prerequisites
A resource break having Unscheduled status must exist.
System Effects
As a result of this activity:
	- the status of the break changes from Unscheduled
	to Finished. 
- if the break belongs to a CBS site, it 
	will be removed from the Scheduling Server.
- if the break belongs to an Advanced Planning Board (APB) site, it will not be loaded when the APB 
	is used.
Window
Resource Break
Related Window Descriptions
Resource Break
Resource Breaks
Procedure
  - Populate the window.
- Select the resource break(s) you want to reject.
- Right-click and then click 
	Reject. The status of the selected break(s) changes to Finished.