Import Maintenance Workload
Explanation
This activity is used to import tasks from IFS/Maintenance. These tasks are considered resource breaks within CBS. Neither Maintenance break dates and times nor CBS break times can be modified.
Prerequisites
This activity has the following prerequisites:
  - IFS/Maintenance must be installed.
-  Either a CBS site or an Advanced Planning Board (APB) site must be defined 
	and enabled in the 
	
	Scheduling Basic Data window.
The tasks that will be imported as resource 
breaks has to fulfill the following constraints:
  - The task site should be the same site where the 
	import is done for.
-  The task should be connected to a object 
	which represents a work center resource or a tool instance.
- The operational status on the task should 
	be Obstructive.
-  Planned finish date on the task has to be 
	defined and should be before the end of the scheduling horizon
- Planned start date on the task has to be 
	defined and should be after the start of the scheduling horizon.
-  The task status should be
	
	Under Preparation, Prepared, Released or Started.
- The execution time ( planned start/finish) needs to be defined on the 
	task.
System Effects
As a result of this activity:
  - The system deletes corresponding resource breaks for any closed or 
	canceled tasks when importing. 
-  The imported tasks are compared against the corresponding resource breaks. Any updated 
	tasks will update the corresponding resource breaks 
	and the new tasks will create new resource breaks.
Window
Maintenance Import
Related Window Descriptions
Maintenance Import
Procedure A
  - In the Site field, specify the site to which you want to import the maintenance 
	tasks. Use List to select from available sites.
- In the Work Center No field, specify for which work center you want to import
    maintenance tasks. Use 
  List to select 
	from available work centers. If you specify no work center, tasks for all work centers
    are imported. As an alternative to specifying the work 
	center number, you can specify the name of the tool that will be used for 
	importing Maintenance task in the Tool ID field. If you 
	specify no tool ID, tasks for all tool IDs are imported.
- In the Resource ID field, specify for which resource you want to import maintenance 
	tasks. 
	Click List to select from available resources. If you specify no resource ID, 
	tasks for all resource IDs are imported. As an alternative to specifying the resource, you have the option of specifying the name of the tool instance in the 
	Tool Instance field. If you specify no tool instance, tasks for all tool instances are imported. 
	specify no tool ID,tasks for all tool IDs are imported.
- In the Begin Date Offset and End Date Offset fields, specify the offset in number of days.specify no tool ID, tasks for all tool IDs are imported.
- Click OK. 
Procedure B
Click Schedule and follow the steps in the wizard.