Attach Parts to Handling Units for Production Schedule Receipt
Explanation
Use this activity to attach the parts to be received into handling units. 
The parts to be received will be automatically matched to a handling unit on the 
lowest level in the structure respecting the calculated quantity to attach. If required, you can manually move parts between the handling 
units to make sure it reflects how the finished goods have been physically packed. 
The icons in the tree structure will indicate the 
quantity attached to the handling unit relative to the planned quantity to attach:
	
		|  | No quantity from this receipt has been 
		attached to the handling unit or the handling units below it. | 
	
		|  | A quantity from this receipt has been attached 
		to the handling unit and/or the handling units below it. However, the 
		accumulated quantity attached is less than the accumulated max capacity 
		for the handling unit. | 
	
		|  | The accumulated quantity attached for this 
		handling unit and the handling units below, is equal to the 
		accumulated max capacity for the handling unit. | 
	
		|  | The accumulated quantity attached for this handling unit and the 
		handling units below, is higher than the accumulated max capacity for 
		the handling unit. | 
Prerequisites
To perform this activity, packing instruction should 
have been defined for the production schedule receipt.
System Effects
As a result of this activity:
	- Handling unit(s) will be generated according to 
	the selected packing instruction(s). Number of handling units on the 
	lowest level in the packing instruction will be generated considering the 
	max capacity defined for the part and the quantity to receive.
- Parts to be received will be attached to the 
	lowest level 
	handling units starting from the one with the lowest handling unit ID 
	respecting the max capacity defined for the part and unit of measure.
Window
Production Schedule by Line
Production Schedule by Line Part
Production Line
Management
Related Window Descriptions
Production Schedule by Line
Production Schedule by Line Part
Production Line Management
Production Line Management/Current Production Schedule
Production Receipt
Attach Parts to Handling Units for Receipt
Move Qty to Handling Unit
Procedure
From Production Schedule by Line window:
	- Search for the production line from which you want to  
	pack and receive.
- Right-click and select Production Receipt.
- Press OK and the Attach Parts to 
	Handling Units for Receipt dialog box will be automatically opened. 
	Part 
	records to be received have been automatically distributed to the handling 
	units respecting their max capacity.
- Review how system has distributed the parts to 
	be received to the handling units by using the tree structure. If required, 
	re-arrange the assignments either by using drag-and-drop directly in the 
	structure, or by using the Move button. The Move Qty to 
	Handling Unit dialog box will appear.
- Enter the quantity to move in the Qty to Move
	field. If the part is catch quantity handled, enter the catch quantity 
	in the Catch Qty to Move field. Click OK.
- If you want serial shipping container code to be 
	generated, select the Create SSCC(s) check box.
- If you want labels to be printed, select the Print 
	Handling Unit Label(s) and/or the Print Handling Unit Contents 
	Label(S) check boxes.
- Click OK.
From the Production Schedule by Line or Production 
Line Management/Current Production Schedule window:
	- Search for the part that you want to pack and receive. 
- Right-click and select Production Receipt.
- Press OK and the Attach Parts to 
	Handling Units for Receipt dialog box will be automatically opened. 
	Part 
	records to be received have been automatically distributed to the handling 
	units respecting their max capacity.
- Review how the system has distributed the parts to 
	be received to the handling units by using the tree structure. If required, 
	re-arrange the assignments either by using drag-and-drop directly in the 
	structure, or by using the Move button. The Move Qty to 
	Handling Unit dialog box will appear.
- Enter the quantity to move in the Qty to Move
	field. If the part is catch quantity handled, enter the catch quantity 
	in the Catch Qty to Move field. Click OK.
- If you want serial shipping container code to be 
	generated, select the Create SSCC(s) check box.
- If you want labels to be printed, select the Print 
	Handling Unit Label(s) and/or the Print Handling Unit Contents 
	Label(S) check boxes.
- Click OK.