Analyze Labor Load Chart
Explanation
This activity is used to analyze the labor load in relation to the 
capacity. Load is represented with bars per day, or week and capacity with a 
line.
To populate the chart, click the magnifying glass and search either for 
relevant shop orders, or labor classes/time period depending on the page used. 
When searching for shop orders, chart will show all load for the relevant labor 
classes and dates.
  The chart can be configured using below settings:
	- Group By - Controls how the bar segments should be 
	divided. 
- Color By - Controls the color of the bar segments. Only 
	available when group by has been set to Operation.
- Load Source - Controls what different types of load 
	that should be considered.
- Capacity Type - Controls whether the capacity line should 
	consider the person utilization or not.
- Load Dates - Controls whether load should be shown only 
	for the dates on 
	which the searched data have load, or all dates within the searched data 
	interval. 
- Aggregate By - Controls whether the X-axis should show 
	load and capacity per day, or per week.
- Show Only Load Dates - Controls whether the X-axis 
	should show only dates with visible load, or include also dates without visible 
	load. Note that if Date Selection has been set to 
	Dates, load may exists on dates even if the load is not visible in 
	the chart as it appears on a date where the search result 
	have no load.
When grouping / coloring by load sources, the below classification is used:
  
    | Load Source | Explanation | 
  
    | Planned | Load from a planned shop order. | 
  
    | Released | Load from a released shop order. | 
  
    | Started | Load from a started shop order. | 
  
    | Parked | Load from a parked shop order. | 
  
    | DOP | Load from an unreleased DOP order. | 
  
    | Requisitioned | Load from a shop order requisition. | 
  
    | Master Schedule | Load from a proposed master production schedule. | 
  
    | Production Schedule | Load from a production schedule. | 
  
    | Promised | Load from a capability check created interim order 
	scheduled using IFS APB/CBS. | 
  
To limit the contents of this chart based on a 
selection made in another chart, open the settings dialog by clicking the 
gearwheel icon and select to filter from any of below charts:
	- Material Availability Summary - Chart is filtered 
	on the shop order(s) of the selected availability category(s). I.e. only 
	date interval and labor classes connected to any operation on these shop 
	orders will be considered.
- Labor Availability Summary - Chart is filtered 
	on the selected labor class(es), work center(s), department(s) or 
	production line(s). I.e. Load and capacity will only be shown for the 
	selected items.
This activity can be performed from IFS Aurena client only.
Prerequisites
	- The labor capacity must have 
been calculated for the site using Calculate Labor Capacity for 
	Manufacturing dialog box. 
- To show loads from sources other then shop order, the capacity 
	requirements planning must be performed for the site using Perform CRP 
	dialog box
System Effects
N/A
Pages
Visual Shop Orders Planning
Visual Capacity Requirements Planning