Add Machine Downtime Result
Explanation
Use this activity to manually register a time result for machine downtime 
registered on a downtime cause.
Prerequisites
To perform this activity, at least one downtime cause 
	must have been entered in the Downtime Causes window. 
System Effects
As a result of this activity, a machine downtime history transaction 
will be 
created.
Window
Shop Floor Reports
Shop Floor 
Workbench
Related Window Descriptions
Add Machine Downtime Result
Shop Floor Reports
Shop Floor Workbench
Shop Floor Workbench/Reports
Procedure
From the Shop Floor Reports window:
	- Right-click and then click Add Machine Downtime Result.
- In the Site field, enter the site or use the list of values to 
	select the site on which the time should be registered. 
- In the Downtime Cause field, use list of values to select the 
	downtime cause on which the time should be registered.
- In the Transaction Date field, enter the date on which the time should be 
	registered.
- In the Work Center field, enter the work 
	center on which the downtime occurred.
- In the Resource field, enter the work 
	center resource on which the downtime occurred.
- In the Time to Report field, enter the 
	downtime in hours to report.
- Click OK. 
From the Shop Floor Workbench 
window:
	- Click the Reports tab and select the Show 
	Downtime Reports
	option.
- Right-click and then click Add Machine Downtime Result.
- In the Site field, enter the site or use the list of values to 
	select the site on which the time should be registered. 
- In the Downtime Cause field, use list of values to select the 
	downtime cause on which the time should be registered.
- In the Transaction Date field, enter the date on which the time should be 
	registered.
- In the Work Center field, enter the work 
	center on which the downtime occurred.
- In the Resource field, enter the work 
	center resource on which the downtime occurred.
- In the Time to Report field, enter the 
	downtime in hours to report.
- Click OK.