Activity Transfer to Standard Inventory 
Explanation
This activity is used to transfer handling units or inventory parts
 from project inventory to
standard inventory.
This may be, for example, when a project has excess material that can be used as 
standard inventory, or when you do not know which other projects will require 
the handling unit or the part. This could also be performed before closing the project, when the 
project is completed. 
This activity also provides for the creation and printing
of new bar codes. Changes in the project belonging of inventory parts
 will affect how the parts are identified using barcodes.
You can enter notes, that will be saved on the resulting inventory 
transactions. 
 
Prerequisites
  - You must select the appropriate handling units 
  or parts in
    project inventory.
- The handling units or parts to be transferred cannot be in transit,
    reserved, or frozen for counting.
System Effects
  - The handling units or parts will be transferred from project inventory to
    standard inventory. 
- The quantity on hand in project inventory will be reduced and those in standard inventory
    will be increased.
    This will be displayed in the windows
    that show inventory on-hand information such as the 
	Inventory Part In Stock 
  or Handling Units in Stock window.
- If you select the Print Barcodes  check box, the
    standard report for printing barcodes will be
    created.
- If notes are entered, they will be saved on each of the inventory 
	transactions that are created.
  
Window
Inventory Part In Stock
Handling Units In Stock
Handling Unit
Related Window Descriptions
Transfer to Standard 
Inventory
Inventory Part in Stock
Transfer Handling Unit 
to Standard Inventory
Handling Units in Stock
Handling Unit/Structure/Handling 
Units
Procedure
From the Inventory Part In Stock window:
  - Populate or query for the parts.
- To transfer the parts to standard inventory, select the appropriate lines with
    the parts in project inventory (i.e., the lines
    displaying project information), and right-click and then click  Transfer to
    Standard Inventory.
- The 
	Transfer to Standard Inventory
    dialog box opens with the project inventory records that you selected.
- The Qty to Transfer field will initially show
    the total quantity of the parts on-hand by default. You can adjust this
    value to transfer any quantity less than or equal to the total quantity of
    the parts on-hand.
- Optionally, you can enter a note text, or select the Print Barcodes 
	check box if new bar codes are to be created.
- Click  OK to transfer the parts to standard inventory.
 
From the   Handling 
Unit/Structure/Handling Units tab and the 
 Handling Unit In 
Stock window:
  - Populate or query for the handling units.
- To transfer the handling units to standard inventory, select the appropriate 
  handling units in project inventory (i.e., the lines where the In 
  Project Inventory check box is selected).  
- Right-click and then click 
	Transfer to
    Standard Inventory.
- The  
	Transfer to Standard Inventory
    dialog box opens for the handling units that you selected.
- Optionally, you can enter a note text.
- Click OK 
	to transfer the handling units to standard inventory.