Phase Out or Replace Structure Component
Explanation
This activity is used to replace a component part in one 
selected structure, several selected structures or in all the structures where 
the component part is included. Depending on what you select in the window such 
as the 
rules for the site and the status on the structure, the outcome will be 
different when a component part is replaced. In some of the scenarios, the 
component part will be replaced in the existing structures and for other 
situations a new revision will be created for the parent part.
Note: Depending on the site rule, structure status, time for the 
phase out and selections in the dialog box, the replacement will either be in existing revisions or new revisions will be created. (Detailed information about the different situations 
are described in the About documentation).
Prerequisites
This activity requires that the component must be defined in the  
Inventory Part window.
System Effects
As a result of this activity, the system replaces a component in a selected 
structure, several selected structures or in all the structures where the 
component part is included, or creates a new inventory part revision for the structures. 
Window
Phase Out or Replace Structure Component
Configuration Structure
Product Structure
Planning Structure
Recipe Structure
Related Window Descriptions
Phase Out or Replace Structure Component
Configuration Structure
Product Structure
Planning Structure
Recipe Structure
Procedure
To replace a component by using a right-click from a structure window
  - Display the parent part by clicking Populate (F2) or by 
  making a selective query (F3).
- On the Structure tab, select the row whose 
	component you want to replace, right-click then click Phase out or 
	Replace Structure Component. The Phase Out or Replace 
	Structure Component dialog box opens.
- The part number for the component to be phased out or replaced is in the
  Part No field. This replacement will follow rules depending 
  on the structure status, structure update level of the site, replacement date 
  and the choices in the dialog box.
- In the Phase Out field, enter the phase-out date to be 
	used when a structure is phased out to accommodate the changes defined in 
	this dialog box.  
- In the Component In area, enter the part number of the 
	component to be phased in in the Part No field. If the 
	window is open from Product, Planning or Configuration Window there is a 
	field for Qty per Assembly field, enter the quantity of 
	the component to constitute one parent part.
- If you select the Copy Configuration check box, all the 
	rules of the old component will be copied to the new component, if not, no 
	rules will be copied. The log, which shows the parts that have rules copied 
	or not can be seen in the background job. 
- If the Structures Exist with Parent Part Phase in Date earlier 
	than Component Part Phase In is selected, a new revision will be 
	created for the parent part. 
- The Update All Effective Structures check box is not 
	available when the window is open from a structure window.
- If the Create New Revision 
	for Buildable 
	check box is selected, the site with structure update level simplified will 
	be handled as enhanced or simplified site. i.e. New revisions will be 
	created when the originating structure is in the Buildable 
	state.
- If you need to create the new revision in the same status as the 
	original structure revision, select the Create Revision in same 
	Status as Existing.
- Click OK.
To replace components by start the dialog from the navigator.
	- Open the Phase out or Replace Structure Component
	dialog box.
- Enter the part number for the component to be phased out or replaced in the Part No 
	field. This replacement will follow rules depending on the structure 
	status, structure update level of the site, replacement date and the choices 
	in the dialog box.
- In the Phase Out field, enter the phase-out date to be 
	used when a structure is phased out to accommodate the changes defined in 
	this dialog box.
- In the Component In area, enter the part number of the 
	component to be phased in in the Part No field. 
- If you select the Copy Configuration check box, all the 
	rules of the old component will be copied to the new component, if not, no 
	rules will be copied. The log, which shows the parts that have rules copied 
	or not can be seen in the background job.
- If the Structures Exist with Parent Part Phase in Date earlier 
	than Component Part Phase In is selected, a new revision will be 
	created for the parent parts that are affected by the criteria.
- If the Update All Effective Structures check box is 
	selected, all the effective structures having the component will be 
	affected. If you need to select specific structures, you need to clear the 
	check box and the table will be populated with all the effective structure.
 Note: A negative 
  value in the Qty per Assembly column indicates that the 
    part is a by-product in the structure.
- If the Create New Revision for Buildable check box is selected, the 
	site with structure update level simplified will be handled as enhanced or 
	simplified site. i.e. New revisions will be created when the originating 
	structure is in the Buildable state.
- If you need to create the new revision in the same status as the 
	original structure revision, select the Create Revision in same 
	Status as Existing.
- Click OK.