Enter Resource Capacity
Explanation
Resource capacity is used when analyzing load from 
planned activities. Resource is defined manually for a certain period of time, 
and the resulting capacity is calculated using the calendar connected to the 
resource, resource group or resource structure.
Prerequisites
A valid calendar must be connected to the resource 
structure.
System Effects
Capacity is calculated and stored by work day in the 
calendar.
Window
Resource Navigator, 
Resource 
Detail, 
Resource Analysis
Related Window Descriptions
Resource Navigator, Resource Detail,
Resource Analysis
Procedure
	- Open the Resource Navigator window
- Search for a resource structure.
- Select a resource group or a resource.
- On the Capacity tab, define manual capacity 
	for one or several time periods in the Resource Quantity for Calculation, Group Utilization(%) and 
	Adjustment(%) fields.
- Alternatively, you can define the manual capacity 
	in the Resource Detail window or in the 
	Resource Analysis window.