Calculate
Explanation
Use this activity to calculated costs, contingency and markups for an item, 
version or all the versions of an estimate. The costs inherited from part cost 
are not re-calculated in cost calculation but any insecurities added on 
inherited costs are added and rolled up to the parent level during calculation.
Prerequisites
	- Default cost elements must be assigned for the estimate cost 
	types in Estimate Cost Type Connections window.
- The items should be active for the costs to be calculated.
- Currency conversion rates should exist in the estimate or in company 
	default currency rate type for the header currency (if the header currency 
	is different from default currency code of the company) and currencies that 
	used in purchase quotations.
System Effects
	- As a result of this activity level and accumulated costs, insecurities and markups of the 
items are calculated.
- Work center costs, labor class costs and currency conversion rates are 
	retrieved.
- Result logs are generated for potential issues in the cost calculations if 
	Generate Log option is selected for the calculation.
- Items will be set to Calculated status.
Window
Estimate
Related Window Descriptions
Estimate
Estimate Items
Procedure
	- Right click on the Estimate window header, a top item or a specific item
- Go to Calculate option and click. Calculate dialog box is opened. Values selected by default vary based on 
	the location from which the dialog box is opened.
- Select All Top Items check box if you want to calculate for 
	all the top items. If you want to calculate for a specific item then clear 
	it and secure that this item is selected in the tree structure.
- Select All Versions check box if you want to calculate cost for 
	all the versions. If you want to calculate cost for a specific version then 
	clear it, secure that the requested version also is the selected version for 
	the estimate.
- Select Execute Online check box if you want to run the calculation online. If the check box is not selected a background job 
	is added for the calculation.
- Select Ignore Standard Lot Size check box if you do not want to 
	consider standard lot size in the calculation, 
- Select Generate Log check box if you want to see the logs for 
	potential problems in cost calculation in the Log tab.
- Click OK.