Define 
Multiple Delivery Overheads
Explanation
This activity is used to register different delivery overheads 
and rates related to the following purchase objects:
	- Supplier for purchase part
- Purchase part
- Supplier
When calculating the cost, the priority will be given 
according to the above order. The Supplier for Purchase 
Part tab in the
Mutiple Delivery Overhead Setup window will be considered first. Then 
the system will check if the Add Delivery OH to the Purchase Part check 
box is selected. If it is selected the system will consider the 
Purchase 
Part tab. If it is not selected then the system will return with the 
overhead cost from the 
Supplier for Purchase Part.. 
If the Add Delivery OH to Supplier check box in 
the 
Purchase Part tab is selected or if no data exist for the 
particular part in this tab, then the delivery overhead cost 
from Supplier tab will also be considered.
When considering costs in the Supplier for Purchase 
Part and 
Supplier tabs, the supplier split functionality 
should also be regarded. If supplier split doesn't exist for a particular part, 
then the primary supplier will be used.
Prerequisites
A cost element for delivery overhead with source 
element 141 
must have been created.
System Effects
The  overhead rates and values specified for the 
cost set will be saved and the records valid for effective date for cost 
calculation will be 
used when calculating costs for the part.
Window
Mutiple Delivery Overhead Setup
Supplier for 
Purchase Part
Purchase Part
Supplier
Related Window Descriptions
Multiple Delivery OH 
Setup
Multiple Delivery OH Setup/Supplier for 
Purchase Part
Multiple Delivery OH Setup/Purchase 
Part
Multiple Delivery OH Setup/Supplier
Supplier for Purchase 
Part/Delivery Overheads
Purchase Part/Delivery 
Overheads
Supplier
Procedure
Supplier for Purchase Part Delivery Overheads
	- Open the 
	Mutiple Delivery Overhead Setup 
	window and query for the cost element ID.
- Click the 
	Supplier for Purchase Part 
	tab and create a new record.
- Enter site, part number, supplier and cost set 
	(except cost set 1) in the Site, Part No, Supplier and
	Cost Set fields respectively or select from the List of Values
	.
- In the Start Date field enter start date 
	for the overhead (The correct start date should be entered to ensure a valid 
	delivery overhead record is picked for effective date for cost calculation).
	
- If required, enter the end date in the End Date 
	field (The end date should be entered correctly so that a valid delivery overhead 
	record is picked for effective date of cost calculation). 
- In the Overhead Rate field, enter the 
	required overhead rate.
- In the Overhead Unit field select the overhead 
	unit from the menu provided.
- If you want to include the purchase part delivery overheads 
	defined for the cost set, click the Add Delivery OH to Purchase Part check box.
- Save the record.
Or
	- Open the 
	Supplier for Purchase Part window.
- On the Delivery Overheads tab, create a new record.
- In the Cost Element ID 
	field, enter the cost element ID or select from the List of Values.
- Follow steps 4 to 9 above.
Purchase Part Delivery Overheads
	- Open the 
	Mutiple Delivery Overhead Setup 
	window and query for the cost element ID.
- Click the 
	Purchase Part tab and 
	create a new record.
- Enter site, part number and cost set (except cost 
	set1) in the Site, Part No and Cost Set fields 
	respectively or select from the List of Values.
- In the Start Date field, enter start date 
	for the overhead. (The correct start date should be entered to ensure valid 
	delivery overhead record is picked for effective date of cost calculation).
- If required, enter the end date in the End Date 
	field. (The
	end date should be entered correctly so that valid delivery overhead 
	record is picked for effective date of cost calculation).
- In the Overhead Rate field enter the 
	required overhead rate.
- In the Overhead Unit field select overhead 
	unit.
- If you want to include the supplier delivery overheads 
	defined for the cost set, select the Add Delivery OH to Supplier check 
	box. 
- Save the record.
Or
	- Open the
	
	Purchase Part window.
- On the Delivery Overheads tab, create a new record.
- In the Cost Element ID 
	field enter the cost element ID or select from the List of Values. 
	
- Follow steps 4 to 9 above.
Supplier Delivery Overheads
	- Open the 
	Mutiple Delivery Overhead Setup 
	window and query for the cost element ID.
- Click the Supplier tab and create a new record.
- Enter supplier, site and cost set (except cost set 
	1 ) in the Supplier, Site and Cost Set fields 
	respectively or select from the List of Values.
- In the Start Date field, enter the start date 
	for the overhead. (The correct start date should be entered to ensure that a valid 
	delivery overhead record is picked for effective date of cost calculation).
- In the End Date field enter the end date for 
	the overhead if needed (The end date, if needed, must be entered correctly so that 
	a valid delivery overhead record is picked for effective date of cost 
	calculation). 
- In the Overhead Unit field select overhead 
	unit.
- In the Overhead Rate field enter the 
	required overhead rate.
- Save the record.
Or
	- Open the
	
	Supplier window.
- On the Purchase/Delivery Overheads tab, create a new record and enter the cost element ID 
	in the Cost element ID field or select from the List of Values.
- Follow steps 4 to 8 above.
Note: The Effective Date field in All Levels Part Cost Calculation, 
All Parts 
Cost Calculation 
and One Level Part Cost Calculation dialog boxes will be used to sort 
the correct delivery overhead cost.